TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/MIN/47899/2020              (ii). Name of Project for which Forest Land is required : Regularization of 330.1826 ha for open cast mining operations in Peddapalli District - 330.1826 ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Regularization of 330.1826 ha of forest land in Upperlakesaram RF of Peddapalli division for RG OCP-I open cast mining operations in Peddapalli District in favour of M/s.SCCL              (iv). File no. : 8-16/2021-FC              (v). State : Telangana              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 330.1826
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/TG/MIN/47899/202006/08/202027/08/2020   18/04/2021   18/04/2021   18/04/2021 Peddapalli :18/04/2021karimnagar:
  18/04/2021 (Peddapalli)

Telangana:
18/04/2021
Telangana:
18/04/2021
06/06/202121/11/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 28/07/2021  
Replied by State Government (Telangana) on:23/01/2022  
Query raised by MoEFCC,New Delhi on 28/03/2022  
Replied by State Government (Telangana) on:15/07/2022  
Query raised by MoEFCC,New Delhi on 29/09/2022  
Replied by State Government (Telangana) on:02/08/2023  
Query raised by State Government (Telangana) on:12/07/2022  
Replied by Nodal Officer (Telangana) on:15/07/2022  
Query raised by State Government (Telangana) on:28/04/2023  
Replied by Nodal Officer (Telangana) on:14/07/2023  
Query raised by Nodal Officer (Telangana) on:12/07/2022  
Replied by Circle(karimnagar) on:15/07/2022  
Query raised by Nodal Officer (Telangana) on:01/05/2023  
Replied by Circle(karimnagar) on:13/07/2023  
Query raised by Circle (karimnagar) on:12/07/2022  
Replied by DFO (Peddapalli) on:15/07/2022  
Query raised by Circle (karimnagar) on:09/06/2023  
Replied by DFO (Peddapalli) on:20/06/2023  
Query raised by DFO (Peddapalli) on:09/06/2023  
Replied by UA on :13/06/2023  
NOTE:- Stage-I Approval accorded by : Head Office .