Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Adilabad)
|
EDS
|
DFO (Bellampally)
|
04/01/2018
|
It is requested to submit RoFR Act certificate obtained from the District Collector for further consideration of proposal
|
|
2
|
DFO (Bellampally)
|
EDS
|
User Agency (gm_mmr@scclmines.com)
|
04/01/2018
|
It is requested to submit RoFR Act certificate obtained from the District Collector for further consideration of proposal
|
|
3
|
User Agency (gm_mmr@scclmines.com)
|
REPLY
|
DFO (Bellampally)
|
03/05/2018
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Bellampally)
|
REPLY
|
CF (Adilabad)
|
03/05/2018
|
Submitted
|
|
5
|
CF (Adilabad)
|
EDS
|
DFO (Bellampally)
|
03/05/2018
|
Upload Canopy density map
|
|
6
|
DFO (Bellampally)
|
REPLY
|
CF (Adilabad)
|
03/05/2018
|
Submitted
|
|
7
|
Head Office
|
EDS
|
State secretary
|
21/12/2018
|
EDS
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
19/09/2022
|
plz furnish the EDS
|
|
9
|
Nodal Officer
|
EDS
|
CF (Kawal Tiger Reserve)
|
28/10/2022
|
furnish the required information as called for by IRO
|
|