  (i). Proposal No. : FP/TG/IRRIG/14110/2015              (ii). Name of Project for which Forest Land is required : Laying of Pipeline for Lift Irrigation Scheme at Chintalapalem RF, Nalgonda Dist - 0.82 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.82 Ha of Forest Land in Chintalapalem RF of Miryalaguda Range on Nalgonda Division For Laying of Pipeline for Lift Irrigation Scheme in favour of TSIDC, Telangana State              (iv). File no. : GO RT No.128 EFS&T (For-I) dept dt:17.09.2016              (v). State : Telangana              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.82
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/TG/IRRIG/14110/201523/07/201523/07/2015   23/07/2015   23/07/2015   01/08/2015 Nalgonda :01/08/2015Hyderabad:
  06/01/2018 (Nalgonda)

Telangana:
06/01/2018
Telangana:
06/01/2018
17/09/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Nalgonda) on:04/02/2016  
Replied by UA on :04/02/2016  
NOTE:- Stage-I Approval accorded by : State Government .