TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/WATER/8155/2014              (ii). Name of Project for which Forest Land is required : Augmentation of Soreng Water Supply Scheme in West Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Reserve Forest land is required for construction of two nos. of water tanks.              (iv). File no. : 1533/FCA/FEWMD              (v). State : Sikkim              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0126
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/SK/WATER/8155/201406/02/2015aa06/02/2015   06/02/2015   West Territorial :07/02/2015Territorial:
  09/04/2015 (West Territorial)

Sikkim:
09/04/2015
Sikkim:
23/04/2015
23/04/2015
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)
Please wait ...