TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/SK/WATER/23488/2017
(ii). Name of Project for which Forest Land is required :
Augmentation of R.W.S.S at Teniok Shantinagar from Andheri Kholsa in East Sikkim
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Construction of 3 nos of water tank, out of which 2 nos fall within Andheri R.F. To meet up with the accurate demand of water construcyion of these tanks and laying of pipelines are mandatory. 48 to 50 household would benefit from this project.
(iv). File no. :
N/A
(v). State :
Sikkim
(vi). Category of the Project :
Drinking Water
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.055
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/SK/WATER/23488/2017
07/01/2017
18/01/2017
25/01/2017
30/01/2017
29/03/2017
East Territorial
:
11/04/2017
Territorial
:
16/09/2017 (
East Territorial
)
Sikkim
:
18/11/2017
Sikkim
:
18/11/2017
Kolkata
:
18/11/2017
16/11/2017
By :Regional Office
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Stage-I Approval accorded by :
Regional Office
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×