TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/TRANS/26421/2017              (ii). Name of Project for which Forest Land is required : Diversion of forest land for construction of 66 KV Single Circuit Transmission line from 132/66KV Swich Yard at Ravangla to Central university with 66/IIKV. 2x5MVA Sub-Station at Yangang, South Sikkim.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The name of the project is Construction of 66KV Single Circuit Transmission line from 132/66KV Swich Yard at Ravangla to Central university with 66/1 I KV. 2x5MV A Sub-Station at Yangang, South Sikkim. The required area for construction of 6 Nos.Tower within the Forest land is 1.8288 Hectare. The be              (iv). File no. : 3-SKB035/2018-SHI              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.8288
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/26421/201729/05/201731/05/2017   18/08/2017   18/08/2017   19/08/2017 South Territorial :19/08/2017Territorial:
  01/03/2018 (South Territorial)

Sikkim:
01/03/2018
Sikkim:
05/04/2018
Kolkata:
05/04/2018
12/03/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:02/05/2018  
Replied by State Government(Sikkim) on:01/03/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)