Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
21/06/2022
|
As per your telephonic request proposal for necessary action.
|
|
2
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
21/06/2022
|
Details has been updated and sent back to you for your further necessary action.
|
|
3
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
21/06/2022
|
Please fill the point No 11 detail of Violation
|
|
4
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
21/06/2022
|
Details has been updated successfully and sent back for your further necessary action.
|
|
5
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
23/06/2022
|
Shortcoming found in part II - 1- Point No 11 Detail of violation B. Period of violation is wrong mentioned please provide date of violation 2- NPV calculation is wrong needs correction.
|
|
6
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
27/06/2022
|
eds has been rectified and the same forwarded for your further necessary action please.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Jodhpur)
|
15/07/2022
|
1.Compete report of violation with copy of the FIR should be uploaded.
2. Provide the list of the forest officials also, who are responsible for this violation.
|
|
8
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
18/07/2022
|
1.Compete report of violation with copy of the FIR should be uploaded. 2. Provide the list of the forest officials also, who are responsible for this violation.
|
|
9
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
03/08/2022
|
EDS has been rectified and send for your further necessary action please.
|
|
10
|
CF (Jodhpur)
|
REPLY
|
Nodal Officer
|
17/08/2022
|
EDS reply send.
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
04/11/2022
|
EDS Reply
|
|
12
|
Nodal Officer
|
EDS
|
CF (Jodhpur)
|
07/11/2022
|
Kindly provide information as State Government required.
|
|
13
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
11/11/2022
|
Kindly provide information as State Government required.
|
|
14
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
24/11/2022
|
EDS has been rectified and sent back for your further necessary action please
|
|
15
|
CF (Jodhpur)
|
REPLY
|
Nodal Officer
|
28/11/2022
|
EDS has been rectified and required information is attached.
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
08/12/2022
|
Reply attached.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
19/01/2023
|
Pls. EDS Reply
|
|
18
|
Nodal Officer
|
EDS
|
CF (Jodhpur)
|
23/01/2023
|
Kindly provide information as per attached document
|
|
19
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
23/01/2023
|
Kindly provide information as per attached document
|
|
20
|
DFO (Jodhpur Territorial)
|
EDS
|
User Agency (powerapprovals@axisenergy.in)
|
24/01/2023
|
Please rectify the eds and return the same at the earliast for further action
|
|
21
|
User Agency (powerapprovals@axisenergy.in)
|
REPLY
|
DFO (Jodhpur Territorial)
|
23/02/2023
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
02/03/2023
|
EDS Reply forwarded by User Agency and same has been forward for your further necessary action please.
|
|
23
|
CF (Jodhpur)
|
REPLY
|
Nodal Officer
|
11/03/2023
|
EDS Reply Attached.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
27/03/2023
|
Reply is attached.
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
10/05/2023
|
EDS letter dated 10.05.2023.
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
23/05/2023
|
please eds reply
|
|
27
|
Nodal Officer
|
EDS
|
CF (Jodhpur)
|
24/05/2023
|
Kindly provide information as per attached document.
|
|
28
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
25/05/2023
|
Kindly provide information as per attached document.
|
|
29
|
DFO (Jodhpur Territorial)
|
EDS
|
User Agency (powerapprovals@axisenergy.in)
|
13/06/2023
|
please find the letter regarding EDS attached herewith
|
|
30
|
User Agency (powerapprovals@axisenergy.in)
|
REPLY
|
DFO (Jodhpur Territorial)
|
12/07/2023
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
14/07/2023
|
EDS reply forwarded for your further necessary action please.
|
|
32
|
CF (Jodhpur)
|
REPLY
|
Nodal Officer
|
26/07/2023
|
Information has uploaded as sought and compliance attached.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
16/08/2023
|
Reply is attached.
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
21/08/2023
|
EDS reply
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
28/08/2023
|
EDS letter dated 28.08.2023.
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
01/09/2023
|
plz eds replr
|
|
37
|
Nodal Officer
|
EDS
|
CF (Jodhpur)
|
02/09/2023
|
Kindly provide information as required by GOI
|
|
38
|
CF (Jodhpur)
|
EDS
|
DFO (Jodhpur Territorial)
|
05/09/2023
|
Kindly provide information as required by GOI
|
|
39
|
DFO (Jodhpur Territorial)
|
EDS
|
User Agency (powerapprovals@axisenergy.in)
|
06/09/2023
|
You are requested to submit as per higher headquarters eds raise on 28 Aug 2023 and return to this office alongwith your reply for our further necessary action.
|
|
40
|
User Agency (powerapprovals@axisenergy.in)
|
REPLY
|
DFO (Jodhpur Territorial)
|
11/01/2024
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Jodhpur Territorial)
|
REPLY
|
CF (Jodhpur)
|
23/01/2024
|
EDS has been rectified and for your further necessary action please.
|
|
42
|
CF (Jodhpur)
|
REPLY
|
Nodal Officer
|
02/02/2024
|
EDS reply attached.
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
07/02/2024
|
Compliance of EDS is submitted for approval
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
15/02/2024
|
EDS reply
|
|