TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/TRANS/120030/2021              (ii). Name of Project for which Forest Land is required : 132 KV S/C Raisinghnagar - Jetsar (M/s NTPC) Transmission Line, District-Sri Ganganagar, Rajasthan (Total Length 17893 meters).              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 132 KV S/C Transmission line is proposed for Power evacuation from 160 MW Solar Power Plant at Jaitsar installed by NTPC to 132 KV Grid Sub Station Raisinghnagar, District-Sri Ganganagar, Rajasthan (Total Length 17893 meters).              (iv). File no. : 8B/Raj/12/28/2021/FC              (v). State : Rajasthan              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0972
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/RJ/TRANS/120030/202110/02/202104/03/2021   08/03/2021   12/03/2021   16/03/2021 Sriganganagar Territorial :17/03/2021Bikaner:
  15/07/2021 (Sriganganagar Territorial)

Rajasthan:
19/08/2021
Rajasthan:
21/10/2021
Jaipur:
18/11/2021
22/12/2021
By :Regional Office
Rajasthan
31/03/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Rajasthan) on:06/09/2021  
Replied by Circle(Bikaner) on:01/10/2021  
Query raised by Circle (Bikaner) on:19/07/2021  
Replied by DFO (Sriganganagar Territorial) on:26/07/2021  
Query raised by Circle (Bikaner) on:07/09/2021  
Replied by DFO (Sriganganagar Territorial) on:22/09/2021  
Query raised by Circle (Bikaner) on:24/09/2021  
Replied by DFO (Sriganganagar Territorial) on:30/09/2021  
Query raised by DFO (Sriganganagar Territorial) on:23/03/2021  
Replied by UA on :16/04/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Jaipur) on:05/05/2022  
Query raised by State Government (Rajasthan) on:13/05/2022  
Replied by Nodal Officer (Rajasthan) on:20/09/2022  
Query raised by State Government (Rajasthan) on:20/09/2022  
Replied by Nodal Officer (Rajasthan) on:30/12/2024  
Query raised by Nodal Officer on:16/05/2022  
Replied by UA on :06/07/2022  
Query raised by Nodal Officer on:20/10/2022  
Replied by UA on :06/12/2024  
NOTE:- Proposal is pending at State Government for verifying Compliance of Conditions due to EDS raised by RO for Stage-II .