TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/ROAD/35272/2018              (ii). Name of Project for which Forest Land is required : Construction of Road from Kota to Pator Km 0/0 to 3/0”, District - Karauli (Rajasthan)"              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Road from Kota to Pator Km 0/0 to 3/0 Applied Area 0.6165h.Kota Pator road is an important road which connects no of villages i.e. Kota, Kanwarpura, Karsai, Maholi, Bazidpur and Kailadevi to direct NH-11B Near Pator              (iv). File no. : 8B/RAJ005/2024-JPR              (v). State : Rajasthan              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.5265
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/ROAD/35272/201811/08/201815/11/2018   06/03/2019   09/05/2019   16/12/2019 Karauli Territorial :19/12/2019Bharatpur:
  03/03/2023 (Karauli Territorial)

Rajasthan:
31/03/2023
Rajasthan:
03/09/2024
Jaipur:
15/10/2024
12/11/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Rajasthan) on:24/04/2023  
Replied by Circle(Bharatpur) on:07/07/2023  
Query raised by Nodal Officer (Rajasthan) on:11/08/2023  
Replied by Circle(Bharatpur) on:31/08/2023  
Query raised by Nodal Officer (Rajasthan) on:04/10/2023  
Replied by Circle(Bharatpur) on:23/10/2023  
Query raised by Nodal Officer (Rajasthan) on:24/11/2023  
Replied by Circle(Bharatpur) on:22/08/2024  
Query raised by Circle (Bharatpur) on:10/03/2023  
Replied by DFO (Karauli Territorial) on:20/03/2023  
Query raised by Circle (Bharatpur) on:25/04/2023  
Replied by DFO (Karauli Territorial) on:13/06/2023  
Query raised by Circle (Bharatpur) on:14/06/2023  
Replied by DFO (Karauli Territorial) on:21/06/2023  
Query raised by Circle (Bharatpur) on:18/08/2023  
Replied by DFO (Karauli Territorial) on:18/08/2023  
Query raised by Circle (Bharatpur) on:09/10/2023  
Replied by DFO (Karauli Territorial) on:16/10/2023  
Query raised by Circle (Bharatpur) on:28/11/2023  
Replied by DFO (Karauli Territorial) on:20/08/2024  
Query raised by DFO (Karauli Territorial) on:29/01/2020  
Replied by UA on :19/07/2022  
Query raised by DFO (Karauli Territorial) on:23/08/2022  
Replied by UA on :17/09/2022  
Query raised by DFO (Karauli Territorial) on:18/11/2022  
Replied by UA on :16/12/2022  
Query raised by DFO (Karauli Territorial) on:31/01/2023  
Replied by UA on :06/02/2023  
Query raised by DFO (Karauli Territorial) on:10/05/2023  
Replied by UA on :08/06/2023  
Query raised by DFO (Karauli Territorial) on:28/11/2023  
Replied by UA on :20/05/2024  
Query raised by DFO (Karauli Territorial) on:30/05/2024  
Replied by UA on :07/06/2024  
Query raised by DFO (Karauli Territorial) on:27/06/2024  
Replied by UA on :08/08/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...