Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
08/02/2018
|
please uplod fra certificate
|
|
2
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
05/04/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
12/04/2018
|
Kindly complete the EDS as attached
|
|
4
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
20/04/2018
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
24/04/2018
|
There is difference in non forest land in khasra map.
|
|
6
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
09/06/2018
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
14/06/2018
|
plz Attested all docements
|
|
8
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
19/06/2018
|
The correction have been made as per the instruction received
|
|
9
|
CF (Jaipur)
|
EDS
|
DFO (Dausa Territorial)
|
19/06/2018
|
furnish the eds
|
|
10
|
DFO (Dausa Territorial)
|
REPLY
|
CF (Jaipur)
|
19/06/2018
|
The correction have been made as per the instructions received
|
|
11
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
26/06/2018
|
plz provide the hard copy of proposal immediately
|
|
12
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
04/07/2018
|
All compliance done with hard copies sent.
|
|
13
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
04/07/2018
|
All compliance done with hard copies sent.
|
|
14
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
23/08/2018
|
Kindly provide information as per attached document
|
|
15
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
23/08/2018
|
Kindly provide information as per attached document
|
|
16
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
28/08/2018
|
Kindly provide information as per attached document
|
|
17
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
01/09/2018
|
kindly provide information for points 6,8,10,11 and 12 of the attached letter from PCCF office dated 7/8/2018
|
|
18
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
27/09/2019
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
05/02/2020
|
plz complete the objections eds date 07.08.2018 & remove tha old paper
|
|
20
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
16/06/2020
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
12/09/2020
|
the correction have been made as per instruction received
|
|
22
|
CF (Jaipur)
|
EDS
|
DFO (Dausa Territorial)
|
15/09/2020
|
pls furnish the reqd. eds
|
|
23
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
23/10/2020
|
PLz correct STATEMENT SHOWING DETAILS OF FORESTAREA PROPOSED FOR DIVERSION
|
|
24
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
04/11/2020
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
10/11/2020
|
PLz correct STATEMENT SHOWING DETAILS OF FORESTAREA PROPOSED FOR DIVERSION
|
|
26
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
24/11/2020
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Dausa Territorial)
|
REPLY
|
CF (Jaipur)
|
15/12/2020
|
The correction have been made as per the instruction received
|
|
28
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
16/12/2020
|
Sir, eds has been submitted by dcf
|
|
29
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
08/01/2021
|
All compliance has been done.
|
|
30
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
29/01/2021
|
All compliance has been done.
|
|
31
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
09/02/2021
|
All compliance has been done.
|
|
32
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
01/03/2021
|
1. Please upload and attach point wise reply of EDS raised on 23.08.2018.
2. CCF has to upload and attach his site inspection report.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
01/03/2021
|
1. Please upload and attach point wise reply of EDS raised on 23.08.2018.
2. CCF has to upload and attach his site inspection report.
|
|
34
|
CF (Jaipur)
|
EDS
|
DFO (Dausa Territorial)
|
03/03/2021
|
please furnish the eds
|
|
35
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
10/03/2021
|
Please upload and attach point wise reply of EDS raised on 23.08.2018
|
|
36
|
DFO (Dausa Territorial)
|
REPLY
|
CF (Jaipur)
|
16/03/2021
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
17/03/2021
|
the correction have been made as per instruction received
|
|
38
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
23/03/2021
|
the correction have been made as per instruction received
|
|
39
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
21/06/2021
|
dcf has been submitted reqd. eds
|
|
40
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
29/06/2021
|
The following shortcomings are found in the proposal-
1. CA scheme should be proposed at one division only as only 100 plants are to be planted. CA scheme should be given given rational a nd site specific.
2. DCF karauli reply did not receive in hard copy.
3. The letter no. given by CCF are not in hard copy, so submit the letters.
4. Land required for diversion should be verified with the record available with the division. Correct forest boundary should be marked
5. If deemed forest land is involved in the proposal, then it should be included.
|
|
41
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
29/06/2021
|
The following shortcomings are found in the proposal-
1. CA scheme should be proposed at one division only as only 100 plants are to be planted. CA scheme should be given given rational a nd site specific.
2. DCF karauli reply did not receive in hard copy.
3. The letter no. given by CCF are not in hard copy, so submit the letters.
4. Land required for diversion should be verified with the record available with the division. Correct forest boundary should be marked
5. If deemed forest land is involved in the proposal, then it should be included.
|
|
42
|
CF (Jaipur)
|
EDS
|
DFO (Dausa Territorial)
|
08/07/2021
|
The following shortcomings are found in the proposal- 1. CA scheme should be proposed at one division only as only 100 plants are to be planted. CA scheme should be given given rational a nd site specific. 2. DCF karauli reply did not receive in hard copy. 3. The letter no. given by CCF are not in hard copy, so submit the letters. 4. Land required for diversion should be verified with the record available with the division. Correct forest boundary should be marked 5. If deemed forest land is involved in the proposal, then it should be included.
|
|
43
|
DFO (Dausa Territorial)
|
REPLY
|
CF (Jaipur)
|
14/07/2021
|
The correction have been made as pr instructions received
|
|
44
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
19/07/2021
|
Kindly provide information as per attached document
|
|
45
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
01/09/2021
|
The correction have been made as per instructions received
|
|
46
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
09/09/2021
|
The compliance has been done.
CA Scheme to be proposed by DCF Dausa for both divisions.
|
|
47
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
20/09/2021
|
The correction have been made as pr instructions received
|
|
48
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
22/09/2021
|
Amount for wall construction by DCf Karauli is incorrect.
|
|
49
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
23/09/2021
|
Amount for wall construction by DCf Karauli is incorrect.
|
|
50
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
24/09/2021
|
Correction have been made as per instructions
|
|
51
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
24/09/2021
|
The compliance has been made as per instruction received.
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
20/12/2021
|
please eds reply
|
|
53
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
20/12/2021
|
Please find attached EDS for compliance.
|
|
54
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
20/12/2021
|
Please find attached EDS for compliance.
|
|
55
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
20/12/2021
|
Please find attached EDS for compliance.
|
|
56
|
CF (Jaipur)
|
EDS
|
DFO (Dausa Territorial)
|
05/01/2022
|
Please find attached EDS for compliance.
|
|
57
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
16/01/2022
|
Please find attached EDS for compliance.
|
|
58
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
07/02/2022
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Dausa Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
14/02/2022
|
Please find tha attached eds for compliance
|
|
60
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Dausa Territorial)
|
08/03/2022
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Dausa Territorial)
|
REPLY
|
CF (Jaipur)
|
11/03/2022
|
the correction have been made as per the instruction receivd
|
|
62
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
30/03/2022
|
The correction have been made as per the instruction received by DCF Dausa
|
|
63
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
01/04/2022
|
Hard copy of the reply of EDS issued by state govt.has to be submitted by CCF Bharatpur
|
|
64
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
01/04/2022
|
Hard copy of the reply of EDS issued by state govt.has to be submitted by DCF Bharatpur to this office
|
|
65
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
19/04/2022
|
Plz complete the objections
|
|
66
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
29/04/2022
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
17/05/2022
|
no alternative route undertaking is not correct .make it correct and submit hard copy after correction in office.
|
|
68
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
10/07/2022
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
24/08/2022
|
The correction have been made as per the instruction received
|
|
70
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
24/08/2022
|
PLEASE SEND POINT WISE REPLY OF ED ISSUED BY STATE GOVT. LETTER DATED 28 NOV. 2021 IN TABULAR FORMAT & ALSO SUBMIT HARD COPIES TO THIS OFFICE. PLEASE FIND ATTACHED EDS FOR COMPLIANCE.
|
|
71
|
DFO (Karauli Territorial)
|
EDS
|
User Agency (eeskd2004@gmail.com)
|
26/08/2022
|
Plz complete the objections
|
|
72
|
User Agency (eeskd2004@gmail.com)
|
REPLY
|
DFO (Karauli Territorial)
|
16/09/2022
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
28/09/2022
|
The correction have been made as per the instruction received
|
|
74
|
CF (Bharatpur)
|
EDS
|
DFO (Karauli Territorial)
|
11/10/2022
|
All compliance has been done.
|
|
75
|
DFO (Karauli Territorial)
|
REPLY
|
CF (Bharatpur)
|
12/10/2022
|
No action is expected from this office
|
|
76
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
12/10/2022
|
All compliance has been done.
|
|
77
|
Nodal Officer
|
EDS
|
CF (Bharatpur)
|
14/10/2022
|
Enclosers mentioned in the reply to the EDS raised by state govt dated 28.11.2021 are not found. Please send again with relevant enclosures/annexures as mentioned in the reply.
|
|
78
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
14/10/2022
|
Enclosers mentioned in the reply to the EDS raised by state govt dated 28.11.2021 are not found. Please send again with relevant enclosures/annexures as mentioned in the reply.
|
|
79
|
CF (Bharatpur)
|
REPLY
|
Nodal Officer
|
21/10/2022
|
Relevant enclosures/annexures have been dispatched / sent with this office letter no. 6679 dated 11.10.2022
|
|
80
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
02/11/2022
|
Enclosers mentioned in the reply to the EDS raised by state govt dated 28.11.2021 has been send again by this office via letter no. 10203 dt 21-10-2022
|
|
81
|
Nodal Officer
|
REPLY
|
State secretary
|
18/11/2022
|
Reply submitted.
|
|