Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ajmer Territorial)
|
EDS
|
User Agency (mbksgn@gmail.com)
|
13/01/2021
|
Reply EDS Attached
|
|
2
|
User Agency (mbksgn@gmail.com)
|
REPLY
|
DFO (Ajmer Territorial)
|
17/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Ajmer)
|
EDS
|
DFO (Ajmer Territorial)
|
20/04/2021
|
Please reply the EDS
|
|
4
|
DFO (Ajmer Territorial)
|
EDS
|
User Agency (mbksgn@gmail.com)
|
29/04/2021
|
Reply EDS attached
|
|
5
|
User Agency (mbksgn@gmail.com)
|
REPLY
|
DFO (Ajmer Territorial)
|
01/06/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Ajmer Territorial)
|
REPLY
|
CF (Ajmer)
|
09/06/2021
|
Estimate of CA as required
|
|
7
|
CF (Ajmer)
|
EDS
|
DFO (Ajmer Territorial)
|
16/06/2021
|
Plz reply EDS
|
|
8
|
DFO (Ajmer Territorial)
|
REPLY
|
CF (Ajmer)
|
05/07/2021
|
Revised estimate attached
|
|
9
|
CF (Ajmer)
|
EDS
|
DFO (Ajmer Territorial)
|
28/07/2021
|
Plz revise CA scheme as per new format
|
|
10
|
DFO (Ajmer Territorial)
|
REPLY
|
CF (Ajmer)
|
27/08/2021
|
Revised CA Estimate in New Format
|
|
11
|
CF (Ajmer)
|
EDS
|
DFO (Ajmer Territorial)
|
03/09/2021
|
CA scheme is not practical. Labour rate in changed from 01.07.2021. Pls change accordingly and send again
|
|
12
|
DFO (Ajmer Territorial)
|
REPLY
|
CF (Ajmer)
|
21/09/2021
|
New estimate with labor wages as on 01.07.2021 are attached for further process
|
|
13
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
29/09/2021
|
Other CA schemes for rs. 1718074/., 72050/-, and for rs. 995430/- should be removed from additional information of PART II of the proposal.
|
|
14
|
CF (Ajmer)
|
EDS
|
DFO (Ajmer Territorial)
|
30/09/2021
|
Other CA schemes for rs. 1718074/., 72050/-, and for rs. 995430/- should be removed from additional information of PART II of the proposal.
|
|
15
|
DFO (Ajmer Territorial)
|
REPLY
|
CF (Ajmer)
|
08/10/2021
|
As per your instructions all Other CA schemes for rs. 1718074/., 72050/-, and for rs. 995430/- should be removed from additional information of PART II of the proposal.
|
|
16
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
12/10/2021
|
As instructed, Correction has been done by DCF, Ajmer
|
|