TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/Others/21735/2016              (ii). Name of Project for which Forest Land is required : Extention of Kolana air strip at Jhalawar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposel for Extention of Existing run way 1700 mtr. to 3000 mtr. for using 120.4062 hact.forest land at kolana , jhalawar (raj)              (iv). File no. : 8-55/2017-FC              (v). State : Rajasthan              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 120.4062
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/RJ/Others/21735/201607/10/201622/02/2017  13/01/2017  13/10/2016   27/02/2017  11/02/2017  10/01/2017   26/03/2017   26/03/2017 Jhalawar Territorial :26/03/2017Kota:
  27/03/2017 (Jhalawar Territorial)

Rajasthan:
27/06/2017
Rajasthan:
16/10/2017
16/10/201707/11/2017
24/11/2017
13/04/2018
By :Head Office
Rajasthan
28/11/2018
18/07/2019
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Nodal Officer (Rajasthan) on:28/07/2017  
Replied by Circle(Kota) on:12/09/2017  
Query raised by Circle (Kota) on:01/04/2017  
Replied by DFO (Jhalawar Territorial) on:19/05/2017  
Query raised by Circle (Kota) on:30/05/2017  
Replied by DFO (Jhalawar Territorial) on:01/06/2017  
Query raised by Circle (Kota) on:12/06/2017  
Replied by DFO (Jhalawar Territorial) on:19/06/2017  
Query raised by Circle (Kota) on:31/07/2017  
Replied by DFO (Jhalawar Territorial) on:29/08/2017  
Query raised by Circle (Kota) on:05/09/2017  
Replied by DFO (Jhalawar Territorial) on:09/09/2017  
Query raised by DFO (Jhalawar Territorial) on:12/04/2017  
Replied by UA on :14/04/2017  
Query raised by DFO (Jhalawar Territorial) on:30/05/2017  
Replied by UA on :30/05/2017  
Query raised by DFO (Jhalawar Territorial) on:31/05/2017  
Replied by UA on :31/05/2017  
Query raised by DFO (Jhalawar Territorial) on:01/06/2017  
Replied by UA on :01/06/2017  
Query raised by DFO (Jhalawar Territorial) on:13/06/2017  
Replied by UA on :14/06/2017  
Query raised by DFO (Jhalawar Territorial) on:31/07/2017  
Replied by UA on :27/08/2017  
Query raised by DFO (Jhalawar Territorial) on:28/08/2017  
Replied by UA on :28/08/2017  
Query raised by DFO (Jhalawar Territorial) on:05/09/2017  
Replied by UA on :08/09/2017  
NOTE:- Stage-II Approval accorded by : Head Office .