Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Udaipur)
|
EDS
|
DFO (Chittorgarh Territorial)
|
25/08/2021
|
please correct the value of area in part 2 - point 4 Details of Vegetation available in the forest land proposed for diversion
|
|
2
|
DFO (Chittorgarh Territorial)
|
REPLY
|
CF (Udaipur)
|
31/08/2021
|
EDS complete
|
|
3
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
22/09/2021
|
DCF has intimated that the OFC is being laid in ROW of the road, on the other hand NPV calculation has been attached and uploaded in the proposal. This is contradictory, please clarify it as in ROW for OFC laying NPV is exempted.
|
|
4
|
CF (Udaipur)
|
EDS
|
DFO (Chittorgarh Territorial)
|
24/09/2021
|
DCF has intimated that the OFC is being laid in ROW of the road, on the other hand NPV calculation has been attached and uploaded in the proposal. This is contradictory, please clarify it as in ROW for OFC laying NPV is exempted.
|
|
5
|
DFO (Chittorgarh Territorial)
|
EDS
|
User Agency (ashwani.pundir0@gmail.com)
|
16/10/2021
|
Revise Part-2 Uploded. EDS Reply
|
|
6
|
User Agency (ashwani.pundir0@gmail.com)
|
REPLY
|
DFO (Chittorgarh Territorial)
|
18/10/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Chittorgarh Territorial)
|
REPLY
|
CF (Udaipur)
|
20/10/2021
|
Revised Part-2 Uploded
|
|
8
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
29/10/2021
|
Revised Part-2 Uploded by DCF
|
|