Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chittorgarh Territorial)
|
EDS
|
User Agency (ashwani.pundir0@gmail.com)
|
25/08/2021
|
EDS
|
|
2
|
User Agency (ashwani.pundir0@gmail.com)
|
REPLY
|
DFO (Chittorgarh Territorial)
|
25/08/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Udaipur)
|
EDS
|
DFO (Chittorgarh Territorial)
|
05/10/2021
|
DCF has intimated that the OFC is being laid in ROW of the road, on the other hand NPV calculation has been attached and uploaded in the proposal. This is contradictory, please clarify it as in ROW for OFC laying NPV is exempted.
|
|
4
|
DFO (Chittorgarh Territorial)
|
EDS
|
User Agency (ashwani.pundir0@gmail.com)
|
16/10/2021
|
Part-II Revised Uploaded. EDS Reply
|
|
5
|
User Agency (ashwani.pundir0@gmail.com)
|
REPLY
|
DFO (Chittorgarh Territorial)
|
19/10/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Chittorgarh Territorial)
|
REPLY
|
CF (Udaipur)
|
20/10/2021
|
Part-II Revised Uploaded. EDS Reply
|
|
7
|
CF (Udaipur)
|
EDS
|
DFO (Chittorgarh Territorial)
|
15/11/2021
|
please find the attached and do the needful
|
|
8
|
DFO (Chittorgarh Territorial)
|
REPLY
|
CF (Udaipur)
|
15/11/2021
|
eds reply
|
|
9
|
CF (Udaipur)
|
EDS
|
DFO (Chittorgarh Territorial)
|
15/11/2021
|
please find the attached and do the needful
|
|
10
|
DFO (Chittorgarh Territorial)
|
EDS
|
User Agency (ashwani.pundir0@gmail.com)
|
29/11/2021
|
EDS
|
|
11
|
User Agency (ashwani.pundir0@gmail.com)
|
REPLY
|
DFO (Chittorgarh Territorial)
|
09/12/2021
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Chittorgarh Territorial)
|
REPLY
|
CF (Udaipur)
|
10/12/2021
|
EDS Reply
|
|