TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/TRANS/9131/2015              (ii). Name of Project for which Forest Land is required : 220 KV T/Line Makhu-Rashiana              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 220 KV Transmission Line from 400 KV s/s Makhu to 220 KV s/s Rashiana              (iv). File no. : FCA/1980/113/2015              (v). State : Punjab              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.426
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/TRANS/9131/201508/01/2015aa08/01/2015   26/03/2015 Ferozepur :27/03/2015Ferozepur Circle:
  07/05/2015 (Ferozepur)

Punjab:
27/05/2015
Punjab:
27/05/2015
26/05/2015
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Ferozepur) on:10/04/2015  
Replied by UA on :15/04/2015  
NOTE:- Stage-I Approval accorded by : State Government .