TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/TRANS/42211/2019              (ii). Name of Project for which Forest Land is required : 66KV line Bhasmra T-off from Devigarh to Roharhjagir line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This line started from village lehla jagir and ends at village Bhasmra under District Patiala and Forest Division Patiala.Power Sector in India has played a very vital role in Socio-Economic development. The fast growth of industrial and agriculture sectors in the country is mostly attributable to t              (iv). File no. : FOREST-FCA0FC2P/43/2020-FCA              (v). State : Punjab              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0594
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/TRANS/42211/201924/09/201904/10/2019  27/09/2019   09/10/2019  03/10/2019   10/10/2019   16/10/2019 Patiala :17/10/2019South Circle:
  27/11/2019 (Patiala)

Punjab:
19/12/2019
Punjab:
26/12/2019
16/11/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Punjab) on:29/01/2020  
Replied by Nodal Officer (Punjab) on:05/10/2020  
Query raised by Nodal Officer (Punjab) on:29/01/2020  
Replied by Circle(South Circle) on:02/06/2020  
Query raised by Nodal Officer (Punjab) on:16/06/2020  
Replied by Circle(South Circle) on:19/06/2020  
Query raised by Nodal Officer (Punjab) on:29/06/2020  
Replied by Circle(South Circle) on:04/07/2020  
Query raised by Nodal Officer (Punjab) on:27/07/2020  
Replied by Circle(South Circle) on:05/08/2020  
Query raised by Circle (South Circle) on:03/12/2019  
Replied by DFO (Patiala) on:18/12/2019  
Query raised by Circle (South Circle) on:29/01/2020  
Replied by DFO (Patiala) on:01/06/2020  
Query raised by Circle (South Circle) on:16/06/2020  
Replied by DFO (Patiala) on:18/06/2020  
Query raised by Circle (South Circle) on:03/07/2020  
Replied by DFO (Patiala) on:03/07/2020  
Query raised by Circle (South Circle) on:27/07/2020  
Replied by DFO (Patiala) on:05/08/2020  
Query raised by DFO (Patiala) on:22/10/2019  
Replied by UA on :31/10/2019  
Query raised by DFO (Patiala) on:06/11/2019  
Replied by UA on :15/11/2019  
Query raised by DFO (Patiala) on:10/12/2019  
Replied by UA on :18/12/2019  
Query raised by DFO (Patiala) on:04/02/2020  
Replied by UA on :22/05/2020  
Query raised by DFO (Patiala) on:28/07/2020  
Replied by UA on :04/08/2020  
NOTE:- Stage-I Approval accorded by : State Government .