TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/TRANS/15980/2015              (ii). Name of Project for which Forest Land is required : Jhunir-Boha Line T-off 66 KV Line Danewala S/C on D/C Tower              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 66 KV Jhunir-Boha Line T-off 66 KV Line Danewala S/C on D/C Towerin favour of PSPCL is a part of Transmission Networks System which is being developed for the industrial, economical and overall development of the region by constructing the prestigious line. The line is the part of              (iv). File no. : fca/1980/38/2016              (v). State : Punjab              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0054
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/TRANS/15980/201511/10/2015aa13/10/2015   21/10/2015 Mansa :21/10/2015South Circle:
  21/01/2016 (Mansa)

Punjab:
27/01/2016
Punjab:
08/03/2016
03/03/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Mansa) on:19/11/2015  
Replied by UA on :19/12/2015  
Query raised by DFO (Mansa) on:01/01/2016  
Replied by UA on :13/01/2016  
NOTE:- Stage-I Approval accorded by : State Government .