Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
01/03/2017
|
EDS
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
07/03/2017
|
Regarding objection
|
|
3
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
07/03/2017
|
Regarding objection
|
|
4
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
28/03/2017
|
Objection
|
|
5
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Garhshankar)
|
28/03/2017
|
Objection
|
|
6
|
DFO (Rupnagar)
|
EDS
|
User Agency (pwdropar@yahoo.co.in)
|
28/03/2017
|
Please upload original hard copy of FRA Certificate as additional document in part-I online.
|
|
7
|
User Agency (pwdropar@yahoo.co.in)
|
REPLY
|
DFO (Rupnagar)
|
29/03/2017
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
29/03/2017
|
letter No. 8916 dated 29.3.2017 is enclosed with enclosures. User Agency has uploaed Original hard copy of FRA Certificate. Revised DGSPS Map is attached herewith and .KML file is sending through email.
|
|
9
|
DFO (Garhshankar)
|
REPLY
|
CF (Shiwalik Circle)
|
17/04/2017
|
Letter attached herewith.
|
|
10
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
18/04/2017
|
Reply by DFO Rupnagar and DFO Garhshankar vide letter No. 8916 dated 29-3-2017 and letter No. 206 dated 17-4-2017
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
19/04/2017
|
Reply
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
19/04/2017
|
Reply
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
28/04/2017
|
eds
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
02/05/2017
|
Regarding objection
|
|
15
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
02/05/2017
|
Regarding objection
|
|
16
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
09/05/2017
|
objection
|
|
17
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Garhshankar)
|
09/05/2017
|
objection
|
|
18
|
DFO (Garhshankar)
|
REPLY
|
CF (Shiwalik Circle)
|
16/05/2017
|
DGPS Map uploaded successfully. The hard copy of Map send to Nodal Officer (FCA) with letter No.206 Dated 17.4.2017.
|
|
19
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
30/05/2017
|
Revised .KML file and DGSPS Map uploaded on the web site
|
|
20
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Garhshankar)
|
01/08/2017
|
objection
|
|
21
|
DFO (Garhshankar)
|
REPLY
|
CF (Shiwalik Circle)
|
04/08/2017
|
DGPS Map uploaded successfully.
|
|
22
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
04/08/2017
|
Reply be DFO Garhshankar
|
|
23
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
16/03/2018
|
Regarding objection
|
|
24
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
16/03/2018
|
Objection
|
|
25
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Garhshankar)
|
16/03/2018
|
Objection
|
|
26
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
19/03/2018
|
Correct DGPS Map and KML File of Nurpurbedi forest is already uploaded and letter No. 1123 dated 17.5.2017 already forwarded to Nodal Officer (FCA) for further necessary action please.
|
|
27
|
DFO (Garhshankar)
|
REPLY
|
CF (Shiwalik Circle)
|
28/03/2018
|
Objection removed as per attachment.
|
|
28
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
04/04/2018
|
objection removed by DFO Garhshankar.
|
|
29
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
13/06/2018
|
DGPS map of CA Site is not uploaded. Upload the same.
|
|
30
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Garhshankar)
|
13/06/2018
|
Objection
|
|
31
|
DFO (Garhshankar)
|
REPLY
|
CF (Shiwalik Circle)
|
13/06/2018
|
Objection removed by uploading of DGPS & .kml.
|
|
32
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
13/06/2018
|
Reply by DFO Garhshankar
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
13/06/2018
|
Reply
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
13/06/2018
|
Reply
|
|