TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/ROAD/115382/2020              (ii). Name of Project for which Forest Land is required : Widening construction of road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest land for widening construction of road from karoli to Bana Enclave road km o to 1.200 village Nagrota HB. 372 Area closed under section 4 of PLPA 1900 forest Division and District Pathankot.              (iv). File no. : 9-PBB338-2023-CHA              (v). State : Punjab              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.858
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/ROAD/115382/202018/12/202023/12/2020   22/04/2021   22/04/2021   09/12/2022 Pathankot :09/12/2022Bist circle:
  13/12/2022 (Pathankot)

Punjab:
16/12/2022
Punjab:
01/02/2023
Chandigarh:
10/03/2023
30/08/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:10/04/2023  
Replied by State Government(Punjab) on:04/08/2023  
Query raised by State Government (Punjab) on:12/04/2023  
Replied by Nodal Officer (Punjab) on:04/08/2023  
Query raised by Nodal Officer (Punjab) on:03/01/2023  
Replied by Circle(Bist circle) on:20/01/2023  
Query raised by Nodal Officer (Punjab) on:12/04/2023  
Replied by Circle(Bist circle) on:04/07/2023  
Query raised by Circle (Bist circle) on:03/01/2023  
Replied by DFO (Pathankot) on:17/01/2023  
Query raised by Circle (Bist circle) on:17/01/2023  
Replied by DFO (Pathankot) on:17/01/2023  
Query raised by Circle (Bist circle) on:20/04/2023  
Replied by DFO (Pathankot) on:27/06/2023  
Query raised by DFO (Pathankot) on:05/01/2023  
Replied by UA on :16/01/2023  
Query raised by DFO (Pathankot) on:25/04/2023  
Replied by UA on :14/06/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .