TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/PB/Others/27411/2017
(ii). Name of Project for which Forest Land is required :
Laying OFC From Fatehgarh Churria to DBN to Kalanaur LHS of Reliance Jio Infocomm Ltd.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Laying OFC From Fatehgarh Churria to DBN to Kalanaur LHS of Reliance Jio Infocomm Ltd. Total Length=34000Mtr. and 0.75ha
(iv). File no. :
FCA/1980/211/2017
(v). State :
Punjab
(vi). Category of the Project :
Others
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.75
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Stage-I Approval on
Stage-II Approval on
FP/PB/Others/27411/2017
26/07/2017
03/08/2017
03/08/2017
03/08/2017
17/08/2017
Gurdaspur
:
17/08/2017
Bist circle
:
11/09/2017 (
Gurdaspur
)
Punjab
:
02/01/2018
Punjab
:
04/01/2018
02/01/2018
By :State Government
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by Circle (Bist circle) on:
13/09/2017
Replied by DFO (Gurdaspur) on:
28/12/2017
NOTE:-
Stage-I Approval accorded by :
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
CF (Bist circle)
EDS
DFO (Gurdaspur)
13/09/2017
Hard copy of the proposal not received.
2
DFO (Gurdaspur)
REPLY
CF (Bist circle)
28/12/2017
Objection has been removed
EDS History(Stage-II)
×