TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/Others/22854/2016              (ii). Name of Project for which Forest Land is required : For laying of OFC Cable for Reliance Jio Infocomm Ltd              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 1.Laying of OFC from Bathinda-Muktasar distric Bounder To Muktasar Gate Km 16/490 To 40/000=23510M 2. Daanewal Chowk Malout To Dodewala KM 3/700 To 39/150 = 35500M 3. Dodewala To Rajpura              (iv). File no. : fca/1980/31/2017              (v). State : Punjab              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.8538
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/Others/22854/201603/12/201607/12/2016   07/12/2016   10/12/2016   27/12/201627/12/201627/12/2016 Faridkot :30/12/2016Ferozepur Circle:
  06/02/2017 (Faridkot)

Punjab:
14/02/2017
Punjab:
15/03/2017
15/03/2017
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .