TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/Others/17430/2016              (ii). Name of Project for which Forest Land is required : Laying Optical Fiber Cable              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.8208 Ha. of forest land for Laying of Optical Fiber Cable From Nakodar to Mehatpur, Mehatpur to Sangowal to Sutlej Pull Km. 03 to 21.2 L/s (Total Length=18.2 KM) under Forest Division & Distt. Jalandhar              (iv). File no. : FCA/1980/41/2016              (v). State : Punjab              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.8208
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/Others/17430/201606/01/201611/01/2016   15/01/2016   20/01/2016   25/01/2016 Jalandhar :28/01/2016Bist circle:
  29/01/2016 (Jalandhar)

Punjab:
03/02/2016
Punjab:
21/06/2016
17/06/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Punjab) on:18/02/2016  
Replied by Circle(Bist circle) on:25/05/2016  
Query raised by Circle (Bist circle) on:18/02/2016  
Replied by DFO (Jalandhar) on:24/05/2016  
Query raised by DFO (Jalandhar) on:02/03/2016  
Replied by UA on :20/05/2016  
NOTE:- Stage-I Approval accorded by : State Government .