TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/OFC/40493/2019              (ii). Name of Project for which Forest Land is required : BHARAT BROADBAND NETWORK LIMITED              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 2.2022 Hac of Forest land for RoW permission for laying OFC of BBNL of Dasuya Block form Dasuya to Hajipur road and Dasuya to village Rampur via Passi Kandi and village Dadial to Nek Naama link road and from Jiaochak (Jalal Chak) to chak Phala and Dasuya main road (Basoa) to village Mew              (iv). File no. : FCA/1980/173/2019              (v). State : Punjab              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.2022
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/OFC/40493/201901/06/201924/06/2019  21/06/2019  10/06/2019   25/06/2019  24/06/2019  19/06/2019   25/06/2019   04/07/2019 Dasuya :08/07/2019Shiwalik Circle:
  26/07/2019 (Dasuya)

Punjab:
06/08/2019
Punjab:
19/08/2019
Chandigarh:
26/12/2019
26/12/2019
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .