Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Gurdaspur)
|
EDS
|
User Agency (reliancepunjab69@gmail.com)
|
26/02/2019
|
mark location of site on toposheet
|
|
2
|
User Agency (reliancepunjab69@gmail.com)
|
REPLY
|
DFO (Gurdaspur)
|
06/05/2019
|
The correction have been made as per the instruction received
|
|
3
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
21/05/2019
|
hard copy of proposal not received yet.
|
|
4
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
24/05/2019
|
Hard copy has been sent
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
12/06/2019
|
Nothing to be uploaded in Sr. No. 13 of Part II.
|
|
6
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
13/06/2019
|
Nothing to be uploaded in Sr. No. 13 of Part II.
|
|
7
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
14/06/2019
|
objection removed
|
|
8
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
14/06/2019
|
Regarding objection.
|
|
9
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
14/06/2019
|
objection has been removed
|
|
10
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
14/06/2019
|
objection has been removed by DFO Gurdaspur.
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
01/08/2019
|
eds
|
|
12
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
06/08/2019
|
eds
|
|
13
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
06/08/2019
|
Regarding objection.
|
|
14
|
DFO (Gurdaspur)
|
EDS
|
User Agency (reliancepunjab69@gmail.com)
|
22/08/2019
|
regarding objection
|
|
15
|
User Agency (reliancepunjab69@gmail.com)
|
REPLY
|
DFO (Gurdaspur)
|
06/12/2019
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
06/12/2019
|
Objection has been removed
|
|
17
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
09/12/2019
|
Objection has been removed.
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
09/12/2019
|
Reply
|
|