| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
20/05/2022
|
Please upload the Land bank Certificate and copy of Register
|
|
|
2
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
25/05/2022
|
in ofc cases , CA has not been done. so land bank certificate and register is not necessary to upload.
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
27/05/2022
|
In covering letter, User Agency mentioned by your office as private instead of Central PSU. Also upload undertaking regarding Existing ROW
|
|
|
4
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
30/05/2022
|
In covering letter, User Agency mentioned by your office as private instead of Central PSU. Also upload undertaking regarding Existing ROW
|
|
|
5
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
02/06/2022
|
Objection has been removed
|
|
|
6
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
02/06/2022
|
Report has been sent to your office vide D.F.O. Gurdaspur letter No. 384 dated 16-05-2022
|
|