Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Rupnagar)
|
EDS
|
User Agency (xen.ropar@gmail.com)
|
04/01/2021
|
Forwarded to User Agency and FRO, Anandpur Sahib for joint filed verification and report
|
|
2
|
User Agency (xen.ropar@gmail.com)
|
REPLY
|
DFO (Rupnagar)
|
16/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
03/03/2021
|
Objections.
|
|
4
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
04/03/2021
|
Covering and Objection removal letter
|
|
5
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
05/03/2021
|
Objections.
|
|
6
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
05/03/2021
|
Objection removed
|
|
7
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
05/03/2021
|
CA scheme is not uploaded in part-II, Forest area calculations are not shown on approved lay out plan, Area mentioned in item wise break up is not correct
|
|
8
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
05/03/2021
|
Objections.
|
|
9
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
05/03/2021
|
Objection removed and documents uploaded
|
|
10
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
05/03/2021
|
Objection Removed by DFO, Rupnagar.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
25/03/2021
|
eds
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
25/03/2021
|
eds
|
|
13
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
25/03/2021
|
eds
|
|
14
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
30/03/2021
|
Objections
|
|
15
|
DFO (Rupnagar)
|
EDS
|
User Agency (xen.ropar@gmail.com)
|
09/04/2021
|
Please removed objection and upload necessary documents on web portal and hard copy submitted to this office
|
|
16
|
User Agency (xen.ropar@gmail.com)
|
REPLY
|
DFO (Rupnagar)
|
16/04/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
16/04/2021
|
Objection removed and case is forwarded for further necessary action please
|
|
18
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Rupnagar)
|
19/04/2021
|
Objection
|
|
19
|
DFO (Rupnagar)
|
EDS
|
User Agency (xen.ropar@gmail.com)
|
19/04/2021
|
Please upload necessary undertaking and submit hardcopy to this office
|
|
20
|
User Agency (xen.ropar@gmail.com)
|
REPLY
|
DFO (Rupnagar)
|
20/04/2021
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Rupnagar)
|
REPLY
|
CF (Shiwalik Circle)
|
20/04/2021
|
UNDERTAKING REGARDING NFL UPLOADED ON PART -II
|
|
22
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
20/04/2021
|
Objection removed by dfo, Ropar
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
05/05/2021
|
Reply
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
05/05/2021
|
Reply
|
|