TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/PB/Approach/47174/2020              (ii). Name of Project for which Forest Land is required : Approach Road for Ajit Castle (Marriage Palace)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion area of 0.0035 ha of forest land for approach access road to Ajit Castle (Marriage Palace) Situated at Village Bainch on Tanda Road to Hoshiarpur Road 16-17 KM, RHS Tehsil Dasuya (Tanda)              (iv). File no. : FOREST-FCA0FC3D/9/2021-FCA              (v). State : Punjab              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0035
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/PB/Approach/47174/202007/07/202016/07/2020   22/09/2020   22/09/2020   30/03/2021 Dasuya :05/04/2021Shiwalik Circle:
  30/04/2021 (Dasuya)

Punjab:
07/09/2021
Punjab:
30/08/2024
03/09/2024
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Punjab) on:22/09/2021  
Replied by Circle(Shiwalik Circle) on:01/06/2022  
Query raised by Nodal Officer (Punjab) on:15/07/2022  
Replied by Circle(Shiwalik Circle) on:07/03/2024  
Query raised by Nodal Officer (Punjab) on:06/05/2024  
Replied by Circle(Shiwalik Circle) on:05/07/2024  
Query raised by Circle (Shiwalik Circle) on:03/05/2021  
Replied by DFO (Dasuya) on:05/05/2021  
Query raised by Circle (Shiwalik Circle) on:13/05/2021  
Replied by DFO (Dasuya) on:27/08/2021  
Query raised by Circle (Shiwalik Circle) on:23/09/2021  
Replied by DFO (Dasuya) on:19/05/2022  
Query raised by Circle (Shiwalik Circle) on:21/07/2022  
Replied by DFO (Dasuya) on:05/03/2024  
Query raised by Circle (Shiwalik Circle) on:07/05/2024  
Replied by DFO (Dasuya) on:04/07/2024  
Query raised by DFO (Dasuya) on:09/04/2021  
Replied by UA on :29/04/2021  
Query raised by DFO (Dasuya) on:11/02/2022  
Replied by UA on :18/05/2022  
Query raised by DFO (Dasuya) on:13/05/2024  
Replied by UA on :04/07/2024  
NOTE:- Stage-I Approval accorded by : State Government .