Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dasuya)
|
EDS
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
09/04/2021
|
provide the documents as per letter attached
|
|
2
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
REPLY
|
DFO (Dasuya)
|
29/04/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Dasuya)
|
03/05/2021
|
Re-check
|
|
4
|
DFO (Dasuya)
|
REPLY
|
CF (Shiwalik Circle)
|
05/05/2021
|
Objection removed
|
|
5
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Dasuya)
|
13/05/2021
|
Objection
|
|
6
|
DFO (Dasuya)
|
REPLY
|
CF (Shiwalik Circle)
|
27/08/2021
|
FRA & Latest Photo uploaded on Part-'s addl. documents
|
|
7
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
22/09/2021
|
eds
|
|
8
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Dasuya)
|
23/09/2021
|
Please remove objections and send report.
|
|
9
|
DFO (Dasuya)
|
EDS
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
11/02/2022
|
Plz provide project approval letter
|
|
10
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
REPLY
|
DFO (Dasuya)
|
18/05/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Dasuya)
|
REPLY
|
CF (Shiwalik Circle)
|
19/05/2022
|
Objections are removed and documents attached in part-2 's addl documents
|
|
12
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
01/06/2022
|
Objections removed and documents attached in part-2 's addl documents by DFO Dasuya.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
15/07/2022
|
eds
|
|
14
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Dasuya)
|
21/07/2022
|
Please remove objections and send report.
|
|
15
|
DFO (Dasuya)
|
REPLY
|
CF (Shiwalik Circle)
|
05/03/2024
|
objection letter attached dated 05.03.2024
|
|
16
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
07/03/2024
|
Objection removed
|
|
17
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
06/05/2024
|
eds
|
|
18
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Dasuya)
|
07/05/2024
|
eds by HoFF
|
|
19
|
DFO (Dasuya)
|
EDS
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
13/05/2024
|
Please Show the Forest Area in Green Colour in KML File
|
|
20
|
User Agency (vikramjitsingh.karwal@yahoo.com)
|
REPLY
|
DFO (Dasuya)
|
04/07/2024
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Dasuya)
|
REPLY
|
CF (Shiwalik Circle)
|
04/07/2024
|
Documents attached in Part 2
|
|
22
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
05/07/2024
|
eds removed by dfo dasuya
|
|