| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Ludhiana)
|
EDS
|
User Agency (karanmehan2455@gmail.com)
|
15/05/2019
|
Regarding Site Inspection
|
|
|
2
|
User Agency (karanmehan2455@gmail.com)
|
REPLY
|
DFO (Ludhiana)
|
31/08/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (South Circle)
|
EDS
|
DFO (Ludhiana)
|
11/09/2019
|
Regarding objection
|
|
|
4
|
DFO (Ludhiana)
|
REPLY
|
CF (South Circle)
|
12/09/2019
|
objection removed
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
18/09/2019
|
eds
|
|
|
6
|
CF (South Circle)
|
EDS
|
DFO (Ludhiana)
|
19/09/2019
|
Regarding objection
|
|
|
7
|
DFO (Ludhiana)
|
EDS
|
User Agency (karanmehan2455@gmail.com)
|
30/09/2019
|
Objection
|
|
|
8
|
User Agency (karanmehan2455@gmail.com)
|
REPLY
|
DFO (Ludhiana)
|
03/10/2019
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Ludhiana)
|
REPLY
|
CF (South Circle)
|
10/10/2019
|
Objection removed
|
|
|
10
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
10/10/2019
|
Reply by DFO
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
18/10/2019
|
eds
|
|
|
12
|
CF (South Circle)
|
EDS
|
DFO (Ludhiana)
|
18/10/2019
|
Regarding objection
|
|
|
13
|
DFO (Ludhiana)
|
REPLY
|
CF (South Circle)
|
26/11/2019
|
objection removed
|
|
|
14
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
26/11/2019
|
Reply by dfo
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
16/12/2019
|
Undertaking to provide non-forest land/ cost equivalent to non-forest land is not provided.
Encroachment of CA site is seen.
|
|
|
16
|
CF (South Circle)
|
EDS
|
DFO (Ludhiana)
|
17/12/2019
|
Undertaking to provide non-forest land/ cost equivalent to non-forest land is not provided. Encroachment of CA site is seen.
|
|
|
17
|
DFO (Ludhiana)
|
REPLY
|
CF (South Circle)
|
19/12/2019
|
objection removed
|
|
|
18
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
20/12/2019
|
Reply by DFO
|
|