Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
11/01/2019
|
eds
|
|
2
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
11/01/2019
|
eds
|
|
3
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
11/01/2019
|
KML and undertaking
|
|
4
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
11/01/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
14/01/2019
|
correction done
|
|
6
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
15/01/2019
|
eds
|
|
7
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
16/01/2019
|
eds
|
|
8
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
16/01/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
16/01/2019
|
revise KML file
|
|
10
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
16/01/2019
|
for eds
|
|
11
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
16/01/2019
|
eds
|
|
12
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
16/01/2019
|
The correction have been made as per the instruction received
|
|
13
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
16/01/2019
|
for eds
|
|
14
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
16/01/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
16/01/2019
|
kml
|
|
16
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
16/01/2019
|
KML file upload by DFO SAS Nagar
|
|
17
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
06/02/2019
|
eds
|
|
18
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
12/02/2019
|
Objection
|
|
19
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
01/03/2019
|
letter
|
|
20
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
01/03/2019
|
Objection removed by DFO SAS Nagar
|
|
21
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
11/03/2019
|
eds
|
|
22
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
14/03/2019
|
EDS
|
|
23
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
15/04/2019
|
letter
|
|
24
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
15/04/2019
|
objection removed by DFO SAS Nagar.
|
|
25
|
Nodal Officer
|
EDS
|
CF (South Circle)
|
02/05/2019
|
Please update kml file with correct area and also show entry/exit gates in kml file.
|
|
26
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
02/05/2019
|
eds
|
|
27
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
02/05/2019
|
KML file
|
|
28
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
02/05/2019
|
The correction have been made as per the instruction received
|
|
29
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
03/05/2019
|
KML
|
|
30
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
03/05/2019
|
The correction have been made as per the instruction received
|
|
31
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
03/05/2019
|
kml file uploaded
|
|
32
|
CF (South Circle)
|
EDS
|
DFO (SAS Nagar)
|
07/05/2019
|
eds
|
|
33
|
DFO (SAS Nagar)
|
EDS
|
User Agency (casavillaz@gmail.com)
|
07/05/2019
|
kml
|
|
34
|
User Agency (casavillaz@gmail.com)
|
REPLY
|
DFO (SAS Nagar)
|
07/05/2019
|
The correction have been made as per the instruction received
|
|
35
|
DFO (SAS Nagar)
|
REPLY
|
CF (South Circle)
|
07/05/2019
|
kml file
|
|
36
|
CF (South Circle)
|
REPLY
|
Nodal Officer
|
08/05/2019
|
upload KML file by DFO SAS Nagar.
|
|