| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
28/11/2019
|
DFO Pathankot
|
|
|
2
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
30/11/2020
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
01/12/2020
|
DFO
|
|
|
4
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
02/12/2020
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
18/12/2020
|
Site Inspection by CF
|
|
|
6
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
12/01/2021
|
DFO Pathankot
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
17/02/2021
|
eds
|
|
|
8
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
17/02/2021
|
eds
|
|
|
9
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
24/02/2021
|
eds
|
|
|
10
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
24/02/2021
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
02/03/2021
|
eds
|
|
|
12
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
04/03/2021
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
04/03/2021
|
Objection removed
|
|
|
14
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
04/03/2021
|
objection removed
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
25/03/2021
|
eds
|
|
|
16
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
26/03/2021
|
objection Raised by Nodal officer
|
|
|
17
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
05/04/2021
|
EDS
|
|
|
18
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
02/07/2021
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
02/07/2021
|
eds
|
|
|
20
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
08/11/2021
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
08/11/2021
|
letter house Proposal No FP/PB /Approach 30957/2017 Kamaljeet
|
|
|
22
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
08/11/2021
|
Objection has been removed by DFO pathankot
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
07/12/2021
|
eds
|
|
|
24
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
07/12/2021
|
Please provide details sought and send clear site plan and calculation.
|
|
|
25
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
03/01/2022
|
EDS
|
|
|
26
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
03/01/2022
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
03/01/2022
|
Diversion of 0 0034 ha Proposal. FPPBApproach309572017
|
|
|
28
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
11/01/2022
|
Essential details provided by DFO Pathankot. Hereby, forwarding for necessary action.
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
31/01/2022
|
eds
|
|
|
30
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
08/02/2022
|
Revise estimate according to new instructions.
|
|
|
31
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
09/02/2022
|
eds
|
|
|
32
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
18/04/2022
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
18/04/2022
|
Objection removed
|
|
|
34
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
16/05/2022
|
Objection removed by DFO Ptk.
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
23/05/2022
|
Upload the Correct KML of CA Site in part 2 as per new instructions dated 31.03.2022.
|
|
|
36
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
23/05/2022
|
Upload the Correct KML of CA Site in part 2 as per new instructions dated 31.03.2022.
|
|
|
37
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
23/05/2022
|
Objection removed
|
|
|
38
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
24/05/2022
|
Objection removed by DFO Ptk.
|
|
|
39
|
State secretary
|
EDS
|
Nodal Officer
|
25/11/2022
|
eds
|
|
|
40
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
25/11/2022
|
eds
|
|
|
41
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
30/11/2022
|
eds
|
|
|
42
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
05/01/2023
|
EDS
|
|
|
43
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
01/06/2023
|
The correction have been made as per the instruction received
|
|
|
44
|
DFO (Pathankot)
|
EDS
|
User Agency (puranchandhouse@gmail.com)
|
06/06/2023
|
eds
|
|
|
45
|
User Agency (puranchandhouse@gmail.com)
|
REPLY
|
DFO (Pathankot)
|
06/06/2023
|
The correction have been made as per the instruction received
|
|
|
46
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
06/06/2023
|
Objection removed
|
|
|
47
|
CF (Bist circle)
|
EDS
|
DFO (Pathankot)
|
06/06/2023
|
eds
|
|
|
48
|
DFO (Pathankot)
|
REPLY
|
CF (Bist circle)
|
06/06/2023
|
Objection removed
|
|
|
49
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
06/06/2023
|
objection removed by dfo
|
|
|
50
|
Nodal Officer
|
REPLY
|
State secretary
|
29/08/2023
|
Reply
|
|