A. General Details
  (i). Proposal No. : FP/PB/Approach/141902/2021              (ii). Name of Project for which Forest Land is required : M/S Shagun Resorts (Marriage Palace), Situated at Village Gurdaspura Basti, Distt. Sangrur              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.00399 HA. of Forest Land for construction of approach access to M/S Shagun Resorts (Marriage Palace), Situated at Village Gurdaspura Basti, on Ludhiana – Malerkotla – Sangrur Road, SH – 11 at RD 75.360 KM (RHS). Tehsil & Distt. Sangrur (PB). Under Forest Division Sangrur.              (iv). State : Punjab              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.00399
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/PB/Approach/141902/202129/04/202104/05/2021  30/04/2021   04/05/2021  03/05/2021   04/05/2021   13/12/2022 Sangrur :15/12/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sangrur) on:10/01/2023  
Replied by UA on :05/11/2024  
Query raised by DFO (Sangrur) on:03/12/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .