TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/TRANS/153797/2022              (ii). Name of Project for which Forest Land is required : 2X160 MVA ,220/132 KV & 2X20 MVA, 220/33KV Grid Substation with associated 220 KV DC line from 400/200 KV PGCIL Grid Substation, Keonjhar to Turumunga & 132 KV LILO line from 132 KV Polaspanga-Karanjia SC line to Turumunga, Keonjhar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 220 KV DC line from 400/200 KV PGCIL Grid substation, Keonjhar to proposed 220/132 KV & 220/33 KV substation, Turumunga, Keonjhar.              (iv). File no. : 5-ORC576/2023-BHU              (v). State : Orissa              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.435
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/TRANS/153797/202231/03/2022aa31/03/2022   06/04/2022 Keonjhar :08/04/2022Rourkela:
  15/04/2023 (Keonjhar)

Orissa:
20/04/2023
Orissa:
17/05/2023
Bhubaneswar:
29/05/2023
14/03/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhubaneswar) on:30/06/2023  
Replied by State Government(Orissa) on:09/11/2023  
Query raised by State Government (Orissa) on:11/07/2023  
Replied by Nodal Officer (Orissa) on:07/11/2023  
Query raised by Nodal Officer (Orissa) on:11/07/2023  
Replied by Circle(Rourkela) on:18/09/2023  
Query raised by Nodal Officer (Orissa) on:05/10/2023  
Replied by Circle(Rourkela) on:07/11/2023  
Query raised by Circle (Rourkela) on:22/08/2023  
Replied by DFO (Keonjhar) on:29/08/2023  
Query raised by Circle (Rourkela) on:07/10/2023  
Replied by DFO (Keonjhar) on:16/10/2023  
Query raised by DFO (Keonjhar) on:11/04/2022  
Replied by UA on :16/05/2022  
Query raised by DFO (Keonjhar) on:24/05/2022  
Replied by UA on :21/03/2023  
Query raised by DFO (Keonjhar) on:29/08/2023  
Replied by UA on :29/08/2023  
Query raised by DFO (Keonjhar) on:07/10/2023  
Replied by UA on :12/10/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)