Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
25/07/2016
|
Item No. 1 Page No. in the checklist has not been mentioned.
Item No. 2 Authorization letter of project authority attached without the attested signature.
Item No. 4 Number of villages to be benefited have not been mentioned in the details note on the project.
Item No. 5 Forest boundaries within the proposed area are not clearly indicated in the map
Item No. 6 Layout plan of the project is not provided.
Item No. 7 Statement showing the details Forest area involved provided without the signature of the Range Officer and Divisional Forest Officer.
Item No. 8 Statement given the details of non-forest area involved in the proposal has been provided without the signature of the concerned Tahasildar. Sabik records of the Non forest area identified has not been provided.
Item No.
|
|
2
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
02/10/2016
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
06/03/2017
|
Please comply the EDS
|
|
4
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
08/03/2017
|
Please comply the deficiencies raised by the Addl. Pr.CCF, FD & NO, FC Act, O/o the PCCF, Odisha, Bhubaneswar.
|
|
5
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
08/03/2017
|
Please comply the following deficiencies as mentioned in the letter No. 742 dated 7.03.2017 1. The extend of non forest land involved in the entire project is not clear. It is mentioned to be 8.81 Ha. in Form A & in the land schedule it comes to 7.727 Ha. 2. Certificate regarding status of non forest land as on 25.10.1980 form the Tahasildar concerned has not been furnished. 3. the liniar diagram with cross section of the road has not been enclosed in the DP. 4. The DGPS Map is not authenticated by the User agency. 5.KML file of the Forest land proposed for diversion is not provided. 6. CA scheme to be submitted along with diversion proposal. 7. The diversion proposal has to be ringfiled with page numbering.
|
|
6
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
24/05/2017
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
16/06/2017
|
Please make correct online entry of Village Wise Breakup & Component Wise Breakup in Form-A Part-1 & kindly submit hard copy for further action.
|
|
8
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
29/06/2017
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
17/07/2017
|
Please comply the discrepancies mentioned in attached Letter No. 2256 Dated.17.07.2017
|
|
10
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
26/07/2017
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
24/08/2017
|
The correction have been made as per the instruction received from the Nodal Office, FC Act.
|
|
12
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
05/09/2017
|
Please comply the deficiencies raised by the Addl. PCCF, Nodal
|
|
13
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
05/09/2017
|
Deficiencies raised by Addl.PCCF, Nodal has been complied & 4 hard copy of DP set already sent.
|
|
14
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
05/09/2017
|
As there is no alternate for widening of NH-57 except Forest Land. hence proposal for diversion of forest land for said purpose is submitted.
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
20/12/2017
|
Approval accorded by State Govt, under General approval vide letter no 26020 dated 15.12.2017
|
|
16
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
04/01/2018
|
Please take necessary action in the matter at its earliest.
|
|
17
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
10/01/2018
|
please follow the instructions issued by the Govt. of Odisha, F & E Department scrupulously and supervise the construction works of NH-57.
|
|
18
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
31/01/2018
|
NPV of Rs. 63,57,030/- has already been demanded vide this office memo no.66 dated.04.01.2018.
|
|
19
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
03/02/2018
|
you are requested to take necessary action in the matter at your level and report compliance to all concerned immediately.
|
|
20
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
03/02/2018
|
Demand of NPV has already been communicated to the User Agency of Rs.63,57,030 vide this office letter no.66 dt.04.01.2018 they are requested to take necessary action as per guideline.
|
|
21
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
07/02/2018
|
Take necessary action in the matter at your level immediately.
|
|
22
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
13/02/2018
|
As NPV already demanded of Rs.63,57,030/- vide this office letter no.66 dt.04.01.2018 Addl.PCCF FD & NOdal Officer FC Act may be requested to generate online demand.
|
|
23
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
16/02/2018
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Subarnapur)
|
EDS
|
User Agency (eenhbolangir@gmail.com)
|
28/03/2018
|
Executive Enginer, N.H Division, Balangir is requested to generate necessary demand form online & upload in portal for necessary approval from nodal.
|
|
25
|
User Agency (eenhbolangir@gmail.com)
|
REPLY
|
DFO (Subarnapur)
|
25/04/2018
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
28/04/2018
|
NPV has been raised. User Agency requested to submit NPV detail online for necessary approval.
|
|
27
|
CF (Bhawanipatna)
|
EDS
|
DFO (Subarnapur)
|
14/05/2018
|
Follow the instructions issued by the Govt. of Odisha, F & E Department Scrupulously and act accordingly.
|
|
28
|
DFO (Subarnapur)
|
REPLY
|
CF (Bhawanipatna)
|
17/05/2018
|
Please close EDS as NPV already raised.
|
|
29
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
17/05/2018
|
Kindly close the EDS,as the NPV has already been raised.
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
31/05/2018
|
Copy of request Letter No.3781 dated 07.05.2018 of Chief Engineer, National Highways, Odisha is forwarded herewith vide this office letter No.11889 dated 30.05.2018 for necessary action at your end.
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
12/10/2020
|
Approved by State Govt.
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
05/01/2021
|
general approval accorded by State Govt. vide Forest & Environment letter No.26020 dtd.15.12.2017
|
|