Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bamra WL)
|
EDS
|
User Agency (eerw_kuchinda@yahoo.com)
|
30/05/2017
|
Directed to submit hard copy of the proposal 6 sets for further necessary action at this end.
|
|
2
|
User Agency (eerw_kuchinda@yahoo.com)
|
REPLY
|
DFO (Bamra WL)
|
27/07/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bamra WL)
|
EDS
|
User Agency (eerw_kuchinda@yahoo.com)
|
05/08/2017
|
1. The alignment of the road has not shown in the topo sheet no.F45M7, submitted with the application. It is very much required for field verification by the undersigned.
2. The dimension of the forest land required i.e length and width has not mentioned anywhere in the application. It has to submit in order to calculate the actual extent of forest area to be diverted. The existing length and width as well as the length and proposed width has to be clearly mentioned in the application. It is very much necessary for field verification especially to ascertain the number of trees to be cut.
3. The detailed note on the project has not submitted properly. Project description, existing feature enroute salient features of the project road, etc. need to be mentioned along with the project ben
|
|
4
|
User Agency (eerw_kuchinda@yahoo.com)
|
REPLY
|
DFO (Bamra WL)
|
23/08/2017
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bamra WL)
|
EDS
|
User Agency (eerw_kuchinda@yahoo.com)
|
25/01/2018
|
It is to inform that the field inspection of the undersigned with respect to the NH-6 to Tansara side diversion proposal is fixed on 25.01.2018, so you are hereby requested to attend the field inspection on the schedule date.
|
|
6
|
User Agency (eerw_kuchinda@yahoo.com)
|
REPLY
|
DFO (Bamra WL)
|
02/02/2018
|
The correction have been made as per the instruction received
|
|
7
|
CF (Sambalpur)
|
EDS
|
DFO (Bamra WL)
|
14/03/2018
|
Non submission of Proposal
|
|
8
|
DFO (Bamra WL)
|
EDS
|
User Agency (eerw_kuchinda@yahoo.com)
|
04/04/2018
|
|
|
9
|
User Agency (eerw_kuchinda@yahoo.com)
|
REPLY
|
DFO (Bamra WL)
|
07/04/2018
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Bamra WL)
|
EDS
|
User Agency (eerw_kuchinda@yahoo.com)
|
12/04/2018
|
Submission of proposal for diversion of forest land for improvement of road & CD work NH-6 to Tansara under PMGSY package No. OR-18-216.
|
|
11
|
User Agency (eerw_kuchinda@yahoo.com)
|
REPLY
|
DFO (Bamra WL)
|
17/04/2018
|
The correction have been made as per the instruction received
|
|