TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/REHAB/26600/2017              (ii). Name of Project for which Forest Land is required : Relocation of villages situated in Core and Buffer area of Similipal Tiger Reserve              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Relocation of villages situated in Core and Buffer area of Similipal Tiger Reserve              (iv). File no. : 5-ORC388/2019-BHU              (v). State : Orissa              (vi). Category of the Project : Rehabilitation              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 39.59
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/REHAB/26600/201712/06/201723/06/2017  12/06/2017   30/06/2017  21/06/2017   01/07/2017   01/09/2017 Karanjia :01/09/2017Baripada:
  21/09/2017 (Karanjia)

Orissa:
20/02/2019
Orissa:
01/05/2019
Bhubaneswar:
22/06/2019
08/11/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Baripada) on:17/10/2017  
Replied by DFO (Karanjia) on:24/08/2018  
Query raised by Circle (Baripada) on:01/09/2018  
Replied by DFO (Karanjia) on:24/08/2018  
Query raised by Circle (Baripada) on:11/10/2018  
Replied by DFO (Karanjia) on:05/10/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .