TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/RAIL/154542/2022              (ii). Name of Project for which Forest Land is required : Bhalumaska to Singapur Road Doubling Railway Project From Km. 128.95 to 163.725              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Indian Railways has started construction of Koraput-Rayagada New B.G. Rail Link Project (164 Km) in the year 1982-83 and commissioned for the entire project in the year 1996-97 for goods traffic initially. Koraput-Rayagada line popularly known as K-R line of East Coast Railway is a single line secti              (iv). File no. : 5-ORC618/2023-BHU              (v). State : Orissa              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 33.152
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/RAIL/154542/202218/04/202208/02/2023  20/01/2023  20/04/2022   08/02/2023  20/01/2023  17/01/2023   24/01/2023   08/02/2023 Rayagada :09/02/2023Koraput:
  11/10/2023 (Rayagada)

Orissa:
22/11/2023
Orissa:
24/11/2023
Bhubaneswar:
25/11/2023
25/01/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhubaneswar) on:13/12/2023  
Replied by State Government(Orissa) on:25/01/2024  
Query raised by State Government (Orissa) on:16/12/2023  
Replied by Nodal Officer (Orissa) on:25/01/2024  
Query raised by Nodal Officer (Orissa) on:18/12/2023  
Replied by Circle(Koraput) on:24/01/2024  
Query raised by Circle (Koraput) on:13/10/2023  
Replied by DFO (Rayagada) on:22/11/2023  
Query raised by Circle (Koraput) on:18/12/2023  
Replied by DFO (Rayagada) on:24/01/2024  
Query raised by DFO (Rayagada) on:18/02/2023  
Replied by UA on :12/09/2023  
Query raised by DFO (Rayagada) on:20/10/2023  
Replied by UA on :18/11/2023  
Query raised by DFO (Rayagada) on:23/12/2023  
Replied by UA on :19/01/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...