Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Rayagada)
|
EDS
|
User Agency (headhse.vll@vedanta.co.in)
|
28/01/2022
|
hard copy of the DPR is required.
|
|
2
|
User Agency (headhse.vll@vedanta.co.in)
|
REPLY
|
DFO (Rayagada)
|
16/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Rayagada)
|
EDS
|
User Agency (headhse.vll@vedanta.co.in)
|
11/04/2022
|
Tree enumeration list, DGPS survey map of the CA land and authirization certificate is required.
|
|
4
|
User Agency (headhse.vll@vedanta.co.in)
|
REPLY
|
DFO (Rayagada)
|
23/11/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Rayagada)
|
EDS
|
User Agency (headhse.vll@vedanta.co.in)
|
16/02/2023
|
Requested to submit the documents of check list serial No 53 Additional document for Liner Project.
|
|
6
|
User Agency (headhse.vll@vedanta.co.in)
|
REPLY
|
DFO (Rayagada)
|
13/04/2023
|
The correction have been made as per the instruction received
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
01/08/2023
|
For submission of necessary clarification.
|
|
8
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
04/08/2023
|
Please comply the EDS vide this office Memo No. 15684 dated 04.08.2023.
|
|
9
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
18/08/2023
|
Compliance is submitted.
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
28/08/2023
|
Compliance submitted to GoO, FE & CC Deptt. vide this office letter No. 17391 dated 28.8.2023.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
30/09/2023
|
Addl. information sought from the State Govt.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
10/10/2023
|
For necessary compliance
|
|
13
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
18/10/2023
|
Please comply the EDS vide this office Memo No. 20643 dated 17.10.2023.
|
|
14
|
CF (Koraput)
|
EDS
|
DFO (Rayagada)
|
19/10/2023
|
Observations pointed out of GoI need to be complied.
|
|
15
|
DFO (Rayagada)
|
EDS
|
User Agency (headhse.vll@vedanta.co.in)
|
20/10/2023
|
Please submit the Observations pointed out of GoI need to be complied.
|
|
16
|
User Agency (headhse.vll@vedanta.co.in)
|
REPLY
|
DFO (Rayagada)
|
08/11/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Rayagada)
|
REPLY
|
CF (Koraput)
|
13/11/2023
|
compliance submitted
|
|
18
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
13/11/2023
|
Necessary compliance is submitted.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
01/12/2023
|
Compliance submitted to GoI, MOEF & CC, IRO, BBSR vide this office letter No. 22801 dated 22.110.2023.
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
05/12/2023
|
Compliance submitted by PCCF (FD&NO, FCA), O/o the PCCF & HoFF, Odisha vide his office letter dated 22.11.2023.
|
|