Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
07/07/2022
|
EDS
|
|
2
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
10/09/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
11/10/2022
|
Please, submit the NOC from Department of Water Resource, Govt. of Odisha for permission of draw water & NOC from National Highway Authority of India for laying of water pipeline in the RoW of NHAI from Kandra to Nuagaon.
|
|
4
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
16/11/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
17/12/2022
|
During the Site Inspection of the undersigned dt. 06.12.2022 of the project for processing the diversion proposal.
|
|
6
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
13/02/2023
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
31/03/2023
|
Please comply the EDs vide this office Memo No. 6433 dated 31.03.2023.
|
|
8
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
03/04/2023
|
Please comply the EDs vide PCCF office Memo No. 6433 dated 31.03.2023.
|
|
9
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
12/04/2023
|
Compliance of PCCF, FC&NO, FC Act dt. 23.03.2023.
|
|
10
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
17/04/2023
|
comply the EDS
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
31/05/2023
|
Addl. information sought from the State Govt.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
17/06/2023
|
For necessary compliance.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
22/06/2023
|
Please comply the EDS vide this office Memo No. 12608 dated 21.06.2023.
|
|
14
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
22/06/2023
|
Please comply the EDS vide PCCF office Memo No. 12608 dated 21.06.2023.
|
|
15
|
DFO (Keonjhar)
|
EDS
|
User Agency (cbs.sengar@jsw.in)
|
26/06/2023
|
Please, comply the observations of IRO, MoEF&CC, GoI, Bhubaneswar dt. 31.05.2023.
|
|
16
|
User Agency (cbs.sengar@jsw.in)
|
REPLY
|
DFO (Keonjhar)
|
20/10/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
20/10/2023
|
The CA Scheme over 4.02 ha Non-forest land has prepared and duly approved by the Conservator of Forest (Nodal) with a financial outlay of Rs.32,44,800/- and the supporting documents of the identified non-forest Govt. land has been uploaded in the web portal. So the said proposal may please be forwarded.
|
|
18
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
20/10/2023
|
The CA Scheme over 4.02 ha Non-forest land has prepared and duly approved by the Conservator of Forest (Nodal) with a financial outlay of Rs.32,44,800/- and the supporting documents of the identified non-forest Govt. land has been uploaded in the web portal. So the said proposal may please be forwarded.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
25/10/2023
|
Compliance submitted to GoI, MoEF, IRO BBSR vide this office Letter No- 20692 dated 17.10.2023.
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
26/10/2023
|
Compliance furnished by PCCF (FD&NO, FCA) vide Letter No. 20692 dated 17.10.2023.
|
|