TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/Others/9825/2015              (ii). Name of Project for which Forest Land is required : Barbil - Angul Iron Ore Slurry Pipeline Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Iron Ore Slurry Pipeline from Barbil to Angul.              (iv). File no. : 5-ORB428/2020-BHU              (v). State : Orissa              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.99
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/Others/9825/201503/07/201509/07/2015   25/01/2016   27/01/2016   18/04/2016 Keonjhar:  18/04/2016
Deogarh:  18/04/2016
Angul:  18/04/2016
Rourkela:
  20/12/2017 (Deogarh)

Rourkela:
  16/05/2017 (Keonjhar)

Angul:
  24/03/2017 (Angul)

Orissa:
16/11/2019
Orissa:
15/07/2020
Bhubaneswar:
25/08/2020
24/09/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Orissa) on:11/12/2019  
Replied by Circle(Rourkela) on:15/02/2020  
Query raised by Nodal Officer (Orissa) on:11/12/2019  
Replied by Circle(Angul) on:04/03/2020  
Query raised by Circle (Rourkela) on:29/12/2017  
Replied by DFO (Deogarh) on:03/05/2018  
Query raised by Circle (Rourkela) on:17/12/2019  
Replied by DFO (Keonjhar) on:14/02/2020  
Query raised by Circle (Rourkela) on:17/12/2019  
Replied by DFO (Deogarh) on:15/02/2020  
Query raised by Circle (Angul) on:19/12/2019  
Replied by DFO (Angul) on:19/02/2020  
Query raised by DFO (Keonjhar) on:27/04/2016  
Replied by UA on :28/02/2017  
Query raised by DFO (Deogarh) on:30/07/2016  
Replied by UA on :28/02/2017  
Query raised by DFO (Deogarh) on:02/03/2017  
Replied by UA on :08/03/2017  
Query raised by DFO (Deogarh) on:08/03/2017  
Replied by UA on :14/03/2017  
Query raised by DFO (Keonjhar) on:15/03/2017  
Replied by UA on :17/03/2017  
Query raised by DFO (Deogarh) on:17/03/2017  
Replied by UA on :17/03/2017  
Query raised by DFO (Keonjhar) on:17/03/2017  
Replied by UA on :23/03/2017  
Query raised by DFO (Keonjhar) on:25/03/2017  
Replied by UA on :16/05/2017  
Query raised by DFO (Angul) on:21/04/2017  
Replied by UA on :16/05/2017  
Query raised by DFO (Deogarh) on:06/05/2017  
Replied by UA on :16/05/2017  
Query raised by DFO (Deogarh) on:29/05/2017  
Replied by UA on :08/09/2017  
Query raised by DFO (Deogarh) on:06/10/2017  
Replied by UA on :07/10/2017  
Query raised by DFO (Deogarh) on:07/10/2017  
Replied by UA on :07/10/2017  
Query raised by DFO (Deogarh) on:12/10/2017  
Replied by UA on :07/12/2017  
Query raised by DFO (Deogarh) on:02/01/2018  
Replied by UA on :27/04/2018  
Query raised by DFO (Keonjhar) on:21/12/2019  
Replied by UA on :14/02/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...