A. General Details
  (i). Proposal No. : FP/OR/Others/7344/2014              (ii). Name of Project for which Forest Land is required : Proposal for Diversion of Forest Land over 11.371 Ha required for construction of Balangir By-Pass Road under Balangir R & B Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for Diversion of Forest Land over 11.371 Ha required for construction of Balangir By-Pass Road under Balangir R & B Division in Balangir tahasil of Balangir District              (iv). File no. : 5-ORC629/2024-BHU              (v). State : Orissa              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 11.371
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/Others/7344/201416/10/201407/06/2016  24/12/2014  27/10/2014   13/07/2016  03/06/2016  23/12/2014   13/07/2016   04/08/2016 Bolangir :05/08/2016Bhawanipatna:
  16/10/2023 (Bolangir)

Orissa:
23/10/2023
Orissa:
08/01/2024
Bhubaneswar:
20/01/2024
14/03/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Orissa) on:09/11/2023  
Replied by Circle(Bhawanipatna) on:07/12/2023  
Query raised by Circle (Bhawanipatna) on:13/11/2023  
Replied by DFO (Bolangir) on:04/12/2023  
Query raised by DFO (Bolangir) on:09/08/2016  
Replied by UA on :27/09/2020  
Query raised by DFO (Bolangir) on:12/11/2020  
Replied by UA on :30/06/2021  
Query raised by DFO (Bolangir) on:07/03/2022  
Replied by UA on :05/08/2022  
Query raised by DFO (Bolangir) on:13/09/2022  
Replied by UA on :28/06/2023  
Query raised by DFO (Bolangir) on:06/07/2023  
Replied by UA on :18/08/2023  
Query raised by DFO (Bolangir) on:28/11/2023  
Replied by UA on :29/11/2023  