TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/Others/46243/2020              (ii). Name of Project for which Forest Land is required : Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), Odisha Phase-2 Project of GAIL              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Project of GAIL is a part of the Prime Minister Urja Ganga Project. The approximate length of the JHBDPL pipeline is 2600 kms and passes through the Eastern UP, Bihar, Jharkhand, Odisha & West Bengal.              (iv). File no. : 5-ORA456/2021-BHU              (v). State : Orissa              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 65.4036
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/Others/46243/202022/06/202022/06/2020   03/07/2020   07/07/2020   19/01/2021 Rourkela :19/01/2021
Sundargarh :19/01/2021
Jharsuguda :19/01/2021
Bamra WL :19/01/2021
Rairakhol :19/01/2021
Deogarh :19/01/2021
Angul :19/01/2021
Sambalpur:
  10/02/2021 (Rairakhol)

Angul:
  19/02/2021 (Angul)

Sambalpur:
  19/02/2021 (Jharsuguda)

Sambalpur:
  21/02/2021 (Bamra WL)

Rourkela:
  22/02/2021 (Sundargarh)

Rourkela:
  22/02/2021 (Rourkela)

Rourkela:
  23/02/2021 (Deogarh)

Orissa:
23/02/2021
Orissa:
10/03/2021
Bhubaneswar:
16/03/2021
30/03/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Jharsuguda) on:20/01/2021  
Replied by UA on :09/02/2021  
Query raised by DFO (Angul) on:27/01/2021  
Replied by UA on :09/02/2021  
Query raised by DFO (Jharsuguda) on:10/02/2021  
Replied by UA on :15/02/2021  
Query raised by DFO (Sundargarh) on:15/02/2021  
Replied by UA on :15/02/2021  
Query raised by DFO (Rourkela) on:18/02/2021  
Replied by UA on :19/02/2021  
Query raised by DFO (Rourkela) on:19/02/2021  
Replied by UA on :19/02/2021  
Query raised by DFO (Deogarh) on:19/02/2021  
Replied by UA on :19/02/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .