TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/Others/23166/2016              (ii). Name of Project for which Forest Land is required : : Kalamang (Sagasahi)-Dabuna Slurry& Water Pipelines Project of M/s Essar Steel India Ltd.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Diversion proposal of 16.466 Ha. for laying 20” dia. dual pipelines (Slurry & Water), power, and communication cables from Kalamang Ghoraburuni-Sagasahi Block, Koira Tahsil, Sundargarh district to Beneficiation plant at Dabuna under Barbil Tahsil of Keonjhar District.              (iv). File no. : 5-ORC496/2022-BHU              (v). State : Orissa              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 16.466
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/Others/23166/201620/12/201622/12/2016   20/03/2017   21/03/2017   22/03/2017

Keonjhar :22/03/2017


Bonai :22/03/2017

Rourkela:
  22/12/2020 (Keonjhar)

Rourkela:
  23/04/2021 (Bonai)

Orissa:
30/04/2021
Orissa:
20/12/2021
Bhubaneswar:
28/12/2021
25/01/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Keonjhar) on:23/03/2017  
Replied by UA on :26/05/2018  
Query raised by DFO (Bonai) on:23/06/2017  
Replied by UA on :26/05/2018  
Query raised by DFO (Bonai) on:28/05/2018  
Replied by UA on :05/06/2018  
Query raised by DFO (Bonai) on:06/06/2018  
Replied by UA on :24/01/2019  
Query raised by DFO (Bonai) on:30/01/2019  
Replied by UA on :08/12/2020  
Query raised by DFO (Bonai) on:08/01/2021  
Replied by UA on :20/04/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .