TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/8707/2014              (ii). Name of Project for which Forest Land is required : Khandbandh Iron Ore Mines              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The mining lease area over 366.311 ha is confined within latitudes: 210 55’ 40.27579" – 210 57’ 29.90066” (Between ML Boundary pillar No.1 & 16) North and Longitudes: 850 23’12.66888” – 850 24’ 45.86016” (Between ML Boundary pillar No.4 & 29) East as per the survey undertaken by ORSAC by DGPS locat              (iv). File no. : 8-46/2018-FC              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 345.189
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/OR/MIN/8707/201427/01/201728/01/2017   14/03/2017   16/03/2017   20/03/2017 Keonjhar :20/03/2017Rourkela:
  18/12/2017 (Keonjhar)

Orissa:
10/03/2018
Orissa:
11/05/2018
18/06/201812/07/2018
16/11/2018
31/01/2019
By :Head Office
Orissa
17/09/2021
16/12/2021
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Circle (Rourkela) on:15/01/2018  
Replied by DFO (Keonjhar) on:08/03/2018  
Query raised by DFO (Keonjhar) on:22/03/2017  
Replied by UA on :19/08/2017  
Query raised by DFO (Keonjhar) on:23/08/2017  
Replied by UA on :04/10/2017  
Query raised by DFO (Keonjhar) on:13/10/2017  
Replied by UA on :20/10/2017  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 29/11/2021  
Replied by State Government (Orissa) on:07/12/2021  
NOTE:- Stage-II Approval accorded by : Head Office .