  (i). Proposal No. : FP/OR/MIN/39355/2019              (ii). Name of Project for which Forest Land is required : Integrated Lakhanpur-Belpahar-Lilari Opencast Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Lakhanpur OC, Belpahar OC, Lilari OC are running OC of MCL, which are proposed to be integrated into one project. The total mine lease of the project is 4399.246 Ha out which 541.622 Ha have been already diverted. The proposal is for Forest diversion of 417.073 Ha              (iv). File no. : 8-280/1989-FC Vol.              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 417.073
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/OR/MIN/39355/201916/03/201919/03/2019   10/06/2020   11/06/2020   11/06/2020 Jharsuguda :17/06/2020Sambalpur:
  02/07/2021 (Jharsuguda)

Orissa:
19/07/2021
Orissa:
29/11/2021
29/11/202127/12/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 29/12/2021  
Replied by State Government (Orissa) on:02/05/2022  
Query raised by MoEFCC,New Delhi on 02/03/2023  
Replied by State Government (Orissa) on:14/07/2023  
Query raised by MoEFCC,New Delhi on 04/09/2023  
Replied by State Government (Orissa) on:14/11/2023  
Query raised by State Government (Orissa) on:15/01/2022  
Replied by Nodal Officer (Orissa) on:29/04/2022  
Query raised by State Government (Orissa) on:15/04/2023  
Replied by Nodal Officer (Orissa) on:11/07/2023  
Query raised by State Government (Orissa) on:07/09/2023  
Replied by Nodal Officer (Orissa) on:09/11/2023  
Query raised by Nodal Officer (Orissa) on:03/11/2021  
Replied by Circle(Sambalpur) on:29/11/2021  
Query raised by Nodal Officer (Orissa) on:18/01/2022  
Replied by Circle(Sambalpur) on:29/01/2022  
Query raised by Nodal Officer (Orissa) on:17/03/2022  
Replied by Circle(Sambalpur) on:07/04/2022  
Query raised by Nodal Officer (Orissa) on:17/04/2023  
Replied by Circle(Sambalpur) on:08/05/2023  
Query raised by Nodal Officer (Orissa) on:22/06/2023  
Replied by Circle(Sambalpur) on:01/07/2023  
Query raised by Nodal Officer (Orissa) on:07/09/2023  
Replied by Circle(Sambalpur) on:29/09/2023  
Query raised by Nodal Officer (Orissa) on:30/09/2023  
Replied by Circle(Sambalpur) on:17/10/2023  
Query raised by Circle (Sambalpur) on:20/01/2022  
Replied by DFO (Jharsuguda) on:29/01/2022  
Query raised by Circle (Sambalpur) on:23/03/2022  
Replied by DFO (Jharsuguda) on:06/04/2022  
Query raised by Circle (Sambalpur) on:28/04/2023  
Replied by DFO (Jharsuguda) on:02/05/2023  
Query raised by Circle (Sambalpur) on:30/09/2023  
Replied by DFO (Jharsuguda) on:16/10/2023  
Query raised by DFO (Jharsuguda) on:06/07/2020  
Replied by UA on :27/03/2021  
Query raised by DFO (Jharsuguda) on:20/01/2022  
Replied by UA on :21/01/2022  
Query raised by DFO (Jharsuguda) on:30/09/2023  
Replied by UA on :16/10/2023  
NOTE:- Stage-I Approval accorded by : Head Office .