Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jharsuguda)
|
EDS
|
User Agency (integratedlbl2019@gmail.com)
|
06/07/2020
|
EDS vide no 2435 dtd 18.06.2020
|
|
2
|
User Agency (integratedlbl2019@gmail.com)
|
REPLY
|
DFO (Jharsuguda)
|
27/03/2021
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
03/11/2021
|
Please comply EDS to the following shortcomings pointed out vide this office Memo No.18179 dated 28.10.2021.
|
|
4
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
29/11/2021
|
Complied the objection by DFO, Keonjhar Forest Division
|
|
5
|
Head Office
|
EDS
|
State secretary
|
29/12/2021
|
EDS
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
15/01/2022
|
Required information as sought for by GoI, MoEF&CC may be furnished.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
18/01/2022
|
Please furnish compliance to the observations of GoI, MoEF & CC.
|
|
8
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
20/01/2022
|
Furnish compliance to the observations of GoI, MoEF & CC
|
|
9
|
DFO (Jharsuguda)
|
EDS
|
User Agency (integratedlbl2019@gmail.com)
|
20/01/2022
|
The UA has been requested to submit the compliance report on the shortcoming as noticed by MoEF & CC, GoI.
|
|
10
|
User Agency (integratedlbl2019@gmail.com)
|
REPLY
|
DFO (Jharsuguda)
|
21/01/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
29/01/2022
|
Compliance of EDS of Moef from DFO Jsg vide Memo No 487 dtd 28.01.2022
|
|
12
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
29/01/2022
|
Compliance of EDS
|
|
13
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
17/03/2022
|
The compliance to the observation of MoEF & CC GoI are found to be incomplete vide this office memo No.5004 dated 16.03.2022.
|
|
14
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
23/03/2022
|
Observation of MoEF & CC
|
|
15
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
06/04/2022
|
Compliance report on the observation of the CCF (Nodal)
|
|
16
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
07/04/2022
|
Comply the Compliance
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
29/04/2022
|
Observation complied vide this office letter No. 9084 dated 29.04.2022 for onward transmission to the Ministry.
|
|
18
|
State secretary
|
REPLY
|
Head Office
|
02/05/2022
|
Compliance furnished by CCF (FD&NO) FC Act, O/o PCCF, Odisha vide letter dtd.29.04.2022.
|
|
19
|
Head Office
|
EDS
|
State secretary
|
02/03/2023
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
15/04/2023
|
For necessary compliance.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
17/04/2023
|
Please comply the EDS vide this office Memo No. 4795 dated 10.03.2023.
|
|
22
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
28/04/2023
|
Please comply the EDS
|
|
23
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
02/05/2023
|
Compliance report on the observation raised by FAC of MoEF & CC, GoI.
|
|
24
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
08/05/2023
|
Compliance report on the observation raised by FAC of MoEF & CC
|
|
25
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
22/06/2023
|
For necessary compliance
|
|
26
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
01/07/2023
|
For necessary compliance report
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
11/07/2023
|
Compliance has been submitted to GoI, MoEF & CC vide this office Letter No. 13828 dated 11.07.2023.
|
|
28
|
State secretary
|
REPLY
|
Head Office
|
14/07/2023
|
Compliance furnished by vide Letter No. 13828 dated 11.07.2023 of PCCF (FD&NO, FC Act), O/o the PCCF & HoFF, Odisha.
|
|
29
|
Head Office
|
EDS
|
State secretary
|
04/09/2023
|
EDS
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
07/09/2023
|
For necessary compliance
|
|
31
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
07/09/2023
|
Please comply the EDS vide this office Memo No. 18081 dated 05.09.2023.
|
|
32
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
29/09/2023
|
Comply the EDS
|
|
33
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
30/09/2023
|
With respect to observation-iii, field verification with respect to earlier diversions obtained under FC Act in six different cases and the proposed change in land use over 171.77 ha in the current Integrated proposal may be verified to ascertain the exact position in the field to certify whether there has been any change in land use without approval.
|
|
34
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
30/09/2023
|
With respect to observation-iii, field verification with respect to earlier diversions obtained under FC Act in six different cases and the proposed change in land use over 171.77 ha in the current Integrated proposal may be verified to ascertain the exact position in the field to certify whether there has been any change in land use without approval.
|
|
35
|
DFO (Jharsuguda)
|
EDS
|
User Agency (integratedlbl2019@gmail.com)
|
30/09/2023
|
The User Agency has been requested to submit the required information for the purpose of filed verification
|
|
36
|
User Agency (integratedlbl2019@gmail.com)
|
REPLY
|
DFO (Jharsuguda)
|
16/10/2023
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
16/10/2023
|
Compliance report on the observation raised by the PCCF, FD & No, FC Act.
|
|
38
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
Comply the EDS
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
09/11/2023
|
Compliance submitted to GoI, MoEF & CC vide this office Letter No. 21861 dated 08.11.2023.
|
|
40
|
State secretary
|
REPLY
|
Head Office
|
14/11/2023
|
Compliance furnsihed by PCCF (FD&NO), FC Act, O/o the PCCF & HoFF, Odisha vide letter dtd.08.11.2023
|
|