Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Cuttack)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
28/04/2018
|
The Certificate under FRA of balance area has not been submitted in the Diversion Proposal.
|
|
2
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Cuttack)
|
29/04/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Cuttack)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
29/06/2018
|
The User AGENCY HAS BEEN REQUESTED TO CORRECTION THE DISTRICT WISE BRECKUP
|
|
4
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Cuttack)
|
02/07/2018
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Angul)
|
23/08/2018
|
Please furnish the point-wise discrepancies pointed out vide this office Memo No.17924 dated 23.08.2018.
|
|
6
|
CF (Angul)
|
EDS
|
DFO (Cuttack)
|
28/08/2018
|
DFO Cuttack to submit compliance on the observation of PCCF Odisha
|
|
7
|
DFO (Cuttack)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
15/10/2018
|
The Proposal has been returned to the User Agency vide this office Memo No.9122 dt.09.10.2018 for necessary compliance.
|
|
8
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Cuttack)
|
20/11/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Cuttack)
|
REPLY
|
CF (Angul)
|
27/12/2018
|
The compliance is submitted herewith for recommendation to higher quarter.
|
|
10
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
25/01/2019
|
Compliance submitted by DFO forwarded
|
|
11
|
IG
|
EDS
|
( MOEFAIG1 )
|
16/10/2019
|
EDS
|
|
12
|
AIG
|
EDS
|
( MOEFTO1 )
|
16/10/2019
|
Stage-I
|
|