Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Angul)
|
EDS
|
User Agency (gm_naini@scclmines.com)
|
11/01/2018
|
The UA has not submitted land scheduled & other documents as per check list
|
|
2
|
User Agency (gm_naini@scclmines.com)
|
REPLY
|
DFO (Angul)
|
07/06/2019
|
The correction have been made as per the instruction received
|
|
3
|
Head Office
|
EDS
|
State secretary
|
21/04/2020
|
EDS
|
|
4
|
State secretary
|
REPLY
|
Head Office
|
10/09/2020
|
Compliance furnished by PCCF Odisha vide letter No15534 dtd04.09.2020
|
|
5
|
Head Office
|
EDS
|
State secretary
|
15/10/2020
|
eds
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
29/12/2020
|
Information called for on the observation of GoI, MoEF & CC vide F & E Deptt. memo No.16912 dtd.29.10.2020
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
02/02/2021
|
The pointwise compliances on deficiencies pointed out by GoI, MoEF & CC vide their letter dated 14.10.2020 is sent herewith vide this office letter No.2067 dated 01.02.2021 for onward transmission.
|
|
8
|
State secretary
|
REPLY
|
Head Office
|
12/02/2021
|
Point wise compliance has been furnished vide Forest & Environment Deptt. letter No.3133/F&E dtd.11.02.2021
|
|