Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
08/12/2017
|
Proposal for Forest Diversion proposal over 697.979 ha. for Pottangi Bauxite Mines, Koraput of M/S NALCO Ltd.,
|
|
2
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
07/11/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
16/12/2019
|
Regarding - Proposal for Forest Diversion Proposal
|
|
4
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
07/02/2020
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
17/02/2020
|
Proposal for Forest Diversion proposal over an area of 679.979 Ha.
|
|
6
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
25/06/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
09/09/2020
|
The proposal for forest diversion proposal over an area of 697.979 Ha.
|
|
8
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
23/09/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
24/09/2020
|
Proposal for Forest Diversion proposal over an area of 679.979 Ha.
|
|
10
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
28/09/2020
|
The correction have been made as per the instruction received
|
|
11
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
03/11/2020
|
CA & Safety Zone scheme need be prepared as per enhanced wage rate.
|
|
12
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
12/02/2021
|
EDS has been complied vide this office Memo No. 696 dated 11.02.2021.
|
|
13
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
15/02/2021
|
CA details has not been filled up correctly in Part-II.
|
|
14
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
19/02/2021
|
EDS has been comlied dated 19.02.2021
|
|
15
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
22/02/2021
|
Compliance to Part-II application
|
|
16
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
22/02/2021
|
EDS has been complied.
|
|
17
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
22/02/2021
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
22/02/2021
|
EDS has been complied vide this office letter dated 22.02.2021.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
01/07/2021
|
Please comply EDS to the deficiencies pointed out vide this office Memo No.10780 dated 01.07.2021.
|
|
20
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
06/07/2021
|
Compliance to objections raised by Nodal Officer
|
|
21
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
19/07/2021
|
Proposal for diversion of 679.979 Ha. of forest land for pottangi bauxite mining lease.
|
|
22
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
21/01/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
21/02/2022
|
In compliance to letter no. 2197 dtd. 6.7.21 and memo no. 115 dtd. 11.1.2022, Revised CA Scheme is enclosed here with
|
|
24
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
24/02/2022
|
Revised CA scheme is submitted.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
07/03/2022
|
EDS has been raised vide this office Memo No. 4336 dated 07.03.2022
|
|
26
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
08/03/2022
|
Compliance to the shortcomings
|
|
27
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
09/03/2022
|
Proposal for forest diversion proposal over an area of 697.979
|
|
28
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
21/06/2022
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
22/06/2022
|
I would like to inform you that after necessary comply with the objections raised vide your office memo under reference.
|
|
30
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
24/06/2022
|
Compliance to the shortcomings need be furnished.
|
|
31
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
24/06/2022
|
Proposal for forest diversion 697.979 ha. of forest land for pottangi bauxite mining lease in village pottangi under pottangi tahasil of koraput district in favour of M/S NALCO Ltd.
|
|
32
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
27/06/2022
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
27/06/2022
|
Compliance for objection point 1 by raised by CCF Nodal.
|
|
34
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
27/06/2022
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
27/06/2022
|
Compliance to objection raised by CCF, Nodal.
|
|
36
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
27/06/2022
|
Compliance submitted.
|
|
37
|
Head Office
|
EDS
|
State secretary
|
28/07/2022
|
eds
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
29/07/2022
|
For necessary compliance.
|
|
39
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
29/07/2022
|
Please comply the EDS raised GoI, MoEF & CC, New Delhi
|
|
40
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
30/07/2022
|
Compliance to the objections
|
|
41
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
03/08/2022
|
Objection raised by CCF, Nodal for proposal for forest diversion of 697.979 Ha. of forest land.
|
|
42
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
23/09/2022
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Koraput)
|
EDS
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
25/09/2022
|
Revised cost benefit analysis is to be submitted.
|
|
44
|
User Agency (kalikinkar.panda@nalcoindia.co.in)
|
REPLY
|
DFO (Koraput)
|
25/09/2022
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
26/09/2022
|
Compliance on observation on GOIMOEF and CC, New Delhi against forest proposal of 697.979 Ha. of Pottangi Bauxite Mines.
|
|
46
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
28/09/2022
|
Compliance to the observations furnished.
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
06/10/2022
|
The compliance to the GoI, MoEF & CC, New Delhi observations dated 27.07.2022 is furnished.
|
|
48
|
State secretary
|
REPLY
|
Head Office
|
07/10/2022
|
Compliance furnished by PCCF (FD&NO), FCA O/o PCCF & HOFF, Odisha vide letter dtd.06.10.2022.
|
|
49
|
Head Office
|
EDS
|
State secretary
|
15/11/2022
|
eds
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
05/12/2022
|
For necessary compliance.
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
07/12/2022
|
EDS has been compliance vide this office Letter No. 24903 dated 07.12.2022.
|
|
52
|
State secretary
|
REPLY
|
Head Office
|
08/12/2022
|
Compliance furnished by PCCF (FD&NO) FC Act, O/o the PCCF & HoFF, Odisha vide letter dt.07.12.2022.
|
|