TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/20736/2016              (ii). Name of Project for which Forest Land is required : Jindal Chromite Mining Lease              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Diversion Proposal over 64.301 ha as per Section 2 (ii) and 66.20 ha as per Section 2 (iii) of FC Act, 1980 of Jindal Chromite Mining Lease.              (iv). File no. : 8-68/2000-Fc pt.              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 66.2
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/OR/MIN/20736/201602/08/201611/08/2016  03/08/2016   11/08/2016  11/08/2016   12/08/2016   12/08/2016 Cuttack :12/08/2016Angul:
  31/01/2019 (Cuttack)

Orissa:
04/10/2019
Orissa:
24/08/2021
03/09/202129/03/2022
By :Head Office
Orissa
10/11/2022
20/04/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 13/10/2021  
Replied by State Government (Orissa) on:06/01/2022  
Query raised by State Government (Orissa) on:26/10/2021  
Replied by Nodal Officer (Orissa) on:04/01/2022  
Query raised by Nodal Officer (Orissa) on:26/11/2019  
Replied by Circle(Angul) on:02/03/2021  
Query raised by Nodal Officer (Orissa) on:30/10/2021  
Replied by Circle(Angul) on:10/12/2021  
Query raised by Circle (Angul) on:12/02/2019  
Replied by DFO (Cuttack) on:03/07/2019  
Query raised by Circle (Angul) on:02/12/2019  
Replied by DFO (Cuttack) on:25/01/2021  
Query raised by Circle (Angul) on:05/11/2021  
Replied by DFO (Cuttack) on:09/11/2021  
Query raised by Circle (Angul) on:12/11/2021  
Replied by DFO (Cuttack) on:07/12/2021  
Query raised by DFO (Cuttack) on:15/08/2016  
Replied by UA on :24/08/2016  
Query raised by DFO (Cuttack) on:08/09/2016  
Replied by UA on :28/11/2018  
Query raised by DFO (Cuttack) on:08/01/2019  
Replied by UA on :31/01/2019  
Query raised by DFO (Cuttack) on:14/02/2019  
Replied by UA on :24/06/2019  
Query raised by DFO (Cuttack) on:13/12/2019  
Replied by UA on :22/01/2021  
Query raised by DFO (Cuttack) on:12/11/2021  
Replied by UA on :05/12/2021  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 20/12/2022  
Replied by State Government (Orissa) on:12/04/2023  
Query raised by State Government (Orissa) on:05/04/2023  
Replied by Nodal Officer (Orissa) on:11/04/2023  
NOTE:- Stage-II Approval accorded by : Head Office .