Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Cuttack)
|
EDS
|
User Agency (ifcal@nic.in)
|
22/07/2016
|
The hard copy of the diversion proposal has not been submitted by the User Agency to this office.
|
|
2
|
User Agency (ifcal@nic.in)
|
REPLY
|
DFO (Cuttack)
|
08/12/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Cuttack)
|
EDS
|
User Agency (ifcal@nic.in)
|
27/03/2017
|
The KML file of the compensatory Afforestation land has not been uploaded.
|
|
4
|
User Agency (ifcal@nic.in)
|
REPLY
|
DFO (Cuttack)
|
06/06/2017
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Cuttack)
|
EDS
|
User Agency (ifcal@nic.in)
|
06/06/2017
|
|
|
6
|
User Agency (ifcal@nic.in)
|
REPLY
|
DFO (Cuttack)
|
22/06/2017
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (Angul)
|
29/08/2017
|
EDS has been complied vide this office Memo No. 18927 dated 28.08.2017.
|
|
8
|
CF (Angul)
|
EDS
|
DFO (Cuttack)
|
30/05/2018
|
DFO Cuttack to comply observations raised by F&E Deptt No24348 dated 24.11.17
|
|
9
|
DFO (Cuttack)
|
EDS
|
User Agency (ifcal@nic.in)
|
22/06/2018
|
The Diversion Proposal has returned to User Agency for comply the deficiencies raised by higher quarter.
|
|
10
|
User Agency (ifcal@nic.in)
|
REPLY
|
DFO (Cuttack)
|
27/10/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Cuttack)
|
REPLY
|
CF (Angul)
|
28/10/2021
|
The CA Scheme, KML File & revised CB Analysis has been enclosed in the DP for onward transmission.
|
|
12
|
CF (Angul)
|
EDS
|
DFO (Cuttack)
|
05/11/2021
|
DFO to comply the observation made by RCCF
|
|
13
|
DFO (Cuttack)
|
EDS
|
User Agency (ifcal@nic.in)
|
11/11/2021
|
The User Agency has been intimated to comply the observations vide this office Letter No.7707 Dt.11-11-2021.
|
|
14
|
User Agency (ifcal@nic.in)
|
REPLY
|
DFO (Cuttack)
|
09/12/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Cuttack)
|
REPLY
|
CF (Angul)
|
09/12/2021
|
The Revised CA Scheme over 14 ha has been prepared as per cost norm of PCCF & HoFF, Odisha and the DPs have been submitted for onward transmission.
|
|
16
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
15/12/2021
|
Proposal for diversion of 22.58 ha of forest land
|
|