Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
04/07/2016
|
Compliance
|
|
2
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
14/04/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
08/05/2018
|
Revise the compensatory afforestation scheme at the current wage rate Rs. 213.50/ Man-day
|
|
4
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
25/06/2018
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
03/07/2018
|
Please, submit the modify/ corrected Form- A
|
|
6
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
09/07/2018
|
The correction have been made as per the instruction received
|
|
7
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
01/08/2018
|
Please comply the eds vide this office Memo No.2410 dated 01.08.2018
|
|
8
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
03/08/2018
|
Quarry reply
|
|
9
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
25/08/2018
|
Please furnish the compliance to the EDS raised by this office Memo No.18025 dated 24.08.2018.
|
|
10
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
10/09/2018
|
Please furnish the compliance to the EDS raised by Addl PCCF Nodal vide his office Memo No.18025 dated 24.08.2018.
|
|
11
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
11/09/2018
|
Submit the point wise compliance report.
|
|
12
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
25/09/2018
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
25/09/2018
|
EDS as regards observation of Addl. PCCF, FD & NO, FC Act vide memo No. 18026 dated 24.08.2018.
|
|
14
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
03/10/2018
|
Compliance with the observations of the Addl.PCCF(FD&NO, FC Act), O/o the PCCF, Odisha vide this office Memo No.3131 Dtd.3.10.2018
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
24/11/2018
|
present status of compliance of order dated 02.08.2017 etc
|
|
16
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
03/12/2018
|
Please furnish the compliance on the observations of State Government in respect of Point No.i to iv immediately communicated vide this office Memo No.24058 dated 01.12.2018
|
|
17
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
10/12/2018
|
Please furnish the compliance on the observations of State Government in respect of Point No.i to iv immediately communicated vide PCCF office Memo No.24058 dated 01.12.2018
|
|
18
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
10/12/2018
|
EDS reply of State Govt. F&E Department, Odisha
|
|
19
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
10/12/2018
|
Comply the EDS
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
02/01/2019
|
The pointwise compliance are furnished herewith vide this office letter No.25645 dated 22.12.2018 for necessary action at your end.
|
|